HomeMy WebLinkAboutCC 12 WTR MAIN REPLACE 9-4-90DATE:
TO:
FROM:
E IDA
AUGUST 29, 1990
WILLIAM A. HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
CONSENT CALENDAR NO. 12
9-4-90
Inter - Com
SUBJECT: AWARD OF CONTRACT FOR WATER MAIN REPLACEMENT ON BROWNING AVENUE,
ENRAMADA DRIVE, ORVILLINA DRIVE, PROJECT NOS. 600070, 600071AND 600073
RECOMMENDATION:
It is recommended that the City Council at their meeting of September 4, 1990 award
the contract for subject project to Tomar Engineering, Inc. of Corona, CA, in the
amount of $110,745.00.
BACKGROUND:
On July 2, 1990, the City Council approved plans and specifications and authorized
the advertisement for bids for the subject project.
This project encompasses the replacement of deteriorated water mains on Browning
Avenue, Enramada Drive and Orvillina Drive in the unincorporated territory of
Orange County.
DISCUSSION:
Sealed bids for this work was received and opened on August 29, 1990 at 10:00 A.M.
and are summarized as follows:
Tomar Engineering, Inc., Corona $110,745.00
Noriega Pipeline, Rancho Cucamonga 119,973.00
Miramontes Construction, Baldwin Park 124,500.00
Vicco Construction, La Verne 125,556.00
Valverde Construction, Whittier 129,230.00
Amick Construction, Ontario 130,030.20
Simich-Masanovich (JV), Arcadia 134,028.00
Construction Engineers, Rosemead 150,245.00
The low bid is 19.9% or $27,541.00 below the engineer's estimate of $138,286.00.
Bob Ledendecker
Director of Public Works/City Engineer
BL: NM: ceg
Nestor Mondok
Junior Civil Engineer
November 1, 1990 Retaining wall on north side of Nisson Road from
Red Hill Avenue to Newport Avenue. Completed.
December 1, 1990 Pile driving on south side of E1 Camino Real from
Red Hill Avenue to Newport Avenue complete.
January 14, 1991 Red Hill Avenue at I-5 restricted to one traffic lane
each way and all freeway on and off ramps closed.
Begin construction of new overcrossing.
March 1, 1991 Retaining wall on south side of E1 Camino Real from
Red Hill Avenue to Newport Avenue complete.
July 1, 1991 Sound wall on north side of Nisson Road from Browning
Avenue and to Red Hill Avenue. Completed.
NOTE: The sound wall on the south side of El Camino
Real from Browning Avenue to Red Hill is being
redesigned and has no schedule at this time.
September 1, 1991 At Red Hill Avenue Freeway southbound off and north-
bound on ramps to be opened.
September 1, 1991 At Newport Avenue Freeway southbound off and north-
bound on ramps to be closed.
October 1992 Red Hill Avenue overcrossing complete including all
ramps. I-5 widening from Jamboree Road to Newport
Avenue. Complete.
A Milestone Schedule for the I-5/SR-55 interchange reconstruction will be submitted
at the next council meeting.
Bob Ledendecker
Director Public Works/City Engineer
BL:ccg