HomeMy WebLinkAboutCC 13 ORANGE ST WIDNG 11-05-90Y DATE: TO: FROM: OCTOBER 31, 1990 WILLIAM A. HUSTON, CITY MANAGER PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION C 'ENT CALENDAR NO. 13 -90 Inter - Com SUBJECT: ORANGE STREET WIDENING/RECONSTRUCTION - HCDA PROJECT RECOMMENDATION: For consideration by the City Council at their meeting of November 5, 1990. It is recommended that the City Council adopt the attached resolution approving the plans and specifications for subject project and directing the City Clerk to advertise for bids. BACKGROUND: This project includes the addition of sidewalk and curb and gutter, as well as asphalt concrete paving to widen the street section of Orange Street, between Bonita Street and Walnut Street, from an existing 30 feet to 36 feet. Also, to improve drainage in this relatively flat area, a storm drain to collect nuisance water, will be constructed. Presently there is $88,800.00 of Housing and Community Development Agency (HCDA) funding available for this project. To ease the burden of a lengthy and phased construction schedule on the area residents, it is recommended that the City fund the remainder of necessary monies, $85,200.00, which may be partially reimbursed through future 16th year HCDA Grant Funds in the amount of $40,000.00. A tentative schedule for this project is as follows: Authorization to Advertise for Bids ............. November 5, 1990 First Legal Advertisement ....................... November 22, 1990 Second Legal Advertisement ...................... November 29, 1990 Bid Opening ..................................... December 11, 1990 Award of Contract ............................... December 17, 1990 Bob Ledendecker Director Public Works/City Engineer BL:WEH:ccg Wendy E`. Hallman Junior Civil Engineer 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 90-141 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA, APPROVING PLANS AND SPECIFICATIONS FOR THE ORANGE STREET WIDENING/RECONSTRUCTION - AN HCDA PROJECT WHEREAS, it is the intention of the City Council of the City of Tustin, California to contract construction of street improvements and storm drain for the widening of Orange Street; and WHEREAS, the City Engineer has presented plans and specifications for the construction of said work; NOW THEREFORE, BE IT RESOLVED, that the plans and specifications presented by the City Engineer be and are hereby approved as the plans and specifications for: Orange Street Widening/Reconstruction an HCDA Project BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to advertise as required by law for the receipt of sealed bids or proposals for the doing of the work specified in the aforesaid plans and specifications; BE IT FURTHER RESOLVED that this project is categorically exempt from the requirements of the California Environmental Quality Act; Class I: Existing Facilities. PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin, held on the 5th day of November, 1990. ATTEST: City Clerk Mayor