HomeMy WebLinkAboutCC 14 WTR MAIN RELOC 11-05-90/000�
DATE:
TO:
FROM:
OCTOBER 31, 1990
WILLIAM A. HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
ONSENT CALENDAR NO. 14
11-5-90
Inter - Com
SUBJECT: FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS - WATER MAIN RELOCATION
ON FIRST STREET, TUSTIN AVENUE AND PASADENA AVENUE (PROD. #600082)
RECOMMENDATION:
That the City Council at their meeting of November 5, 1990 adopt the attached
resolution accepting said work and authorizing the recordation of the Notice
of Completion.
Assuming no claims or stop payment notices are filed, it is further
recommended that 30 days after the date of recordation of the Notice of
Completion that the Council authorize payment of the final 10% retention
amount of $11,802.23. This amount, together with previous payments of
$106,220.03, represents 100% of the final contract amount.
BACKGROUND:
This project encompassed the relocation of the existing water mains on First
Street, Tustin Avenue and Pasadena Avenue, to accommodate Caltrans'
construction of the I-5/SR-55 interchange, Stage II Project. Caltrans issued
Notice to Owner No. 12-004 directing Tustin to relocate the water mains that
interfere with the interchange project. Tustin has prior right easements for
the relocated water mains and will be reimbursed for all project costs by
Caltrans. Per Utility Agreement No. 12004, with the State of California.
The work has been completed to the satisfaction of the Engineering Division.
The final contract amount is $118,022.26. This represents an overrun of 18.2
percent from the original contract amount of $99,840.50
Bob Leden ecker Nestor Mondok
Director Public Works/City Engineer Junior Civil Engineer
BL: NM: ccg
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 90-140
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING WORKS OF IMPROVEMENT AND AUTHORIZING
RECORDATION OF NOTICE OF COMPLETION FOR WATER MAIN RELOCATION
ON FIRST STREET, TUSTIN AVENUE AND PASADENA AVENUE.
WHEREAS, Golem Construction, having a contract with the City of Tustin
to construct the hereinafter described public work and improvement; and
WHEREAS, the City Engineer has duly certified the construction and
completion of said public improvements hereinafter mentioned in a manner
satisfactory to the City Council of the City of Tustin; and
WHEREAS, the City Council finds that said contractor has completed
said public improvement hereinafter more particularly described in
accordance with the provisions of the contract documents and the Notice of
Completion, and acceptance of said public work and improvement should be
filed and payment of the balance due said contract authorized in accordance
with the contract documents.
NOW THEREFORE, BE IT RESOLVED by the City Council of the City of
Tustin that said public work and improvement be, and the same is hereby
accepted. Said public work and improvement is more particularly described
as follows:
Water Main Relocation on First Street, Tustin Avenue
and Pasadena Avenue, Project No. 600082
AND BE IT FURTHER RESOLVED that the City Engineer of the City of
Tustin be and is hereby authorized to execute and file a Notice of
Completion and acceptance of said public work and improvement described
herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City Council of the
City of Tustin on the 5th day of November, 1990.
ATTEST:
City Clerk
p
Mayor