HomeMy WebLinkAboutRPT 4 WARNER BRIDGE 06-19-89TO: WILLIAM HUSTON, CITY MANAGER FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION SUBJECT: WARNER AVENUE BRIDGE CONSTRUCTION STATUS REPORT Information and scheduling has been received from Caltrans covering work scheduled through June 23, 1989. Each schedule covers a two-week period, consequently, we will attempt to provide an update at least once each month. For orientation, the following is nomenclature that will be utilized throughout these schedule updates: , * Abutment #1 - the westerly bridge foundation on the Santa Ana side. * Bent #2 - the columns and foundations at the center of the bridge, located on the centerline of the freeway. * Abutment #3- - the easterly bridge foundation on the Tustin side. * Falsework - the temporary supports utilized to support the super- structure While it is under construction. * Superstructure- that portion or the bridge which spans the travelways of the Rte 55 Freeway. The following recap will cover work ~eing performed Within the periods of June 7., 1989 through June 23, 1989: June 7, 8, 9, 12, 13, 14, 15, 16 Pour and cure the columns along Bent #2. June 8, 9, 12 Drive piles for Abutment #3. June 13, 14, 15, 16 Drive' piles for Abutment #1. June 19, 20, 21 Fabricate caps for columns along Bent #2. June 22 Erect caps for coiumns along Bent #2. freeway lane closures Night work required with some June 15,- 16, 19 Form and place steel for pile cap in Abutment #3. June 20 Pour pile cap on Abutment #3. WARNER AVENUE BRIDGE STATUS REPORT ~JUNE 13, 1989- PAGE 2 June 20, 21, 22 Form and place steel for pile cap in Abutment #1. June 23 Pour pile cap on Abutment .#1. Bob Ledendecker Director of Public Works/City Engineer BL:mv