HomeMy WebLinkAboutCC 12 WTR MAIN REPLACE 07-17-89TO: WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS - WATER MAIN REPLACEMENT
ON REBECCA LANE, GWEN AVENUE, LUCINDA WAY & DEBORAH DRIVE
RECOMMENDATION:
That the City Council at their meeting of July 17, 1989 adopt the
attached resolution accepting said work and authorizing the recordation
of the notice of completion.
Assuming no claims or stop payment notices are filed, it is further
recommended that 30 days after the date of recordation of the notice of
completion that the Council authorize payment of the final 10%
retention amount of $9,811.70. This amount, together with previous
payments of $88,305.20, represents 100% of the final contract amount.
BACKGROUND:
This project encompassed the replacement of the deteriorated water mains
on Rebecca Lane, Gwen Avenue, Lucinda Way, and Deborah Drive within the
unincorporated area of Orange County.
Ail work has been completed to the satisfaction of the Engineering
Division. The original contract amount was for $98,775.00. The final
contract amount is $98,117.00 for an under-run on the contract of 0.6%.
Bob Ledendecker
Director of Public Works/City Engineer
BL:WA:mv
Steve Worrall
Associate Civil Engineer
1
2
5
6
?
8
9
10
11
12
13
15
16
1'1
18
19
20
21
26
28
RESOLUTION NO. 89-106
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUSTIN, CALIFORNIA, ACCEPTING WORKS OF
IMPROVEMENT AND AUTHORIZING RECORDATION OF
NOTICE OF COMPLETION OF WATER MAIN IMPROVEMENTS
ON REBECCA LANE, GWEN AVENUE, LUCINDA WAY AND
DEBORAH DRIVE.
WHEREAS, R.L.T. Construction, having a contract with the
City of Tustin to construct the hereinafter described public
work and improvement; and
WHEREAS, the City Engineer has duly certified to the
construction and completion of said public improvements herein-
after mentioned in a manner satisfactory to the City Council of
the City of Tustin; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinafter more particularly
described in accordance with the provisions of the contract
documents and the notice of completion, and acceptance of said
public work and improvement should be filed and payment of the
balance due said contract authorized in accordance with the
contract documents.
NOW THEREFORE, BE IT RESOLVED by the City Council of the
City of Tustin that said public work and improvement be, and the
same is, hereby accepted. Said public work and improvement is
more particularly described as follows:
Water Main Improvements on Rebecca Lane, Gwen Avenue,
Lucinda Way and Deborah Drive
AND BE IT FURTHER RESOLVED that the City Engineer of the
City of Tustin be and is hereby authorized to execute and file a
notice of completion and acceptance of said public work and
improvement described herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City
Council of the City of Tustin on the day of
of , 1989.
ATTEST:
Mayor
City Clerk