HomeMy WebLinkAboutRPT 3 WARNER BRIDGE 08-07-89TO: WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: WARNER AVENUE BRIDGE CONSTRUCTION STATUS REPORT
This report will provide an update on the subject bridge through August
11, 1989. The only scheduling information that we are receiving from
Caltrans is the weekly report which projects work schedules for a period
of two weeks.
The falsework and forming for the superstructure is currently under way
and is scheduled to be completed by August llth.
The grading for approach embankments on both sides of the Rte 55 freeway
is approximately 80% complete.
Caltrans' resident engineer has indicated that the overall project
appears to be two to three weeks ahead of schedule.
Bob LedeHdecker
Director of Public Works/City Engineer
BL:mv