HomeMy WebLinkAboutRPT 3 WARNER BRIDGE 08-07-89TO: WILLIAM HUSTON, CITY MANAGER FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION SUBJECT: WARNER AVENUE BRIDGE CONSTRUCTION STATUS REPORT This report will provide an update on the subject bridge through August 11, 1989. The only scheduling information that we are receiving from Caltrans is the weekly report which projects work schedules for a period of two weeks. The falsework and forming for the superstructure is currently under way and is scheduled to be completed by August llth. The grading for approach embankments on both sides of the Rte 55 freeway is approximately 80% complete. Caltrans' resident engineer has indicated that the overall project appears to be two to three weeks ahead of schedule. Bob LedeHdecker Director of Public Works/City Engineer BL:mv