HomeMy WebLinkAboutRPT 6 WARNER BRIDGE 09-05-89,,..?~ ii! ~,:~ ~ ~ ~ .- REPORTS Int e r - C o m DATE: AUGUST 30, 1989 ~ TO: FROM: SUBJECT: WILLIAM HUSTON, CITY MANAGER PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION WARNER AVENUE BRIDGE CONSTRUCTION STATUS REPORT This report will provide an update on the subject bridge through the week of September 18, 1989. As previously indicated, we are receiving information on a weekly basis that provides work schedules for a period two weeks in advance. The concrete and reinforcing steel placement has been completed on the soffit (bottom side of bridge deck) and the utility installation is scheduled to commence August 30, 1989. Utility installation is scheduled to be completed by September 13, 1989. The concrete placement for the 'bridge deck (driving surface) scheduled to commence during the week of September 18, 1989. is Overall, the project remains two to three weeks ahead of schedule. Director of Public Works/City Engineer BL:mv