DATE: AUGUST 30, 1989 ~
TO:
FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
WARNER AVENUE BRIDGE CONSTRUCTION STATUS REPORT
This report will provide an update on the subject bridge through the
week of September 18, 1989. As previously indicated, we are receiving
information on a weekly basis that provides work schedules for a period
two weeks in advance.
The concrete and reinforcing steel placement has been completed on the
soffit (bottom side of bridge deck) and the utility installation is
scheduled to commence August 30, 1989. Utility installation is
scheduled to be completed by September 13, 1989.
The concrete placement for the 'bridge deck (driving surface)
scheduled to commence during the week of September 18, 1989.
is
Overall, the project remains two to three weeks ahead of schedule.