HomeMy WebLinkAboutNB 1 ASPHALT OVERLAY 09-18-89 TO: WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT:. AWARD OF CONTRACT FOR THE ASPHALTIC CONCRETE PAVEMENT OVERLAY
~ OF EAST TUSTIN STREETS
RECOMMENDATION:
That the Tustin City Council at their meeting of September 18, 1989
award the contract for the subject project to the .low bidder, Sully
Miller Contracting Company of Orange, in the amount of $492,655.85.
BACKGROUND:
The following is a list of assessment district streets that are included
with the proposed overlay project.
* E1 Camino Real between Myford Road and Jamboree Road (AD No.85-1)
* Bryan Avenue between a point easterly of Browning Avenue and
Jamboree Road (AD No. 85-1)
* Irvine Blvd. between a point easterly of Ranchwood Road and
Jamboree Road (South 1/2 - AD No. 85-2 and North 1/2 - AD No. 86-2)
* Tustin Ranch Road between Bryan Avenue and Irvine Blvd.(AD No. 85-1)
* Myford Road between E1 Camino Real and Irvine Blvd. (AD No. 85-1)
The following streets are Irvine Company streets which they have
requested be included within the city contract subject to reimbursement
to the city by The Irvine Company:
, Parkcenter Lane between Bryan Avenue and Tustin Ranch Road
* Heritage Way between Tustin Ranch Road and Bryan Avenue
* Lagier Way between Tustin Ranch Road and Heritage Way
On August 7, 1989, the Tustin City Council approved the plans and
specifications for the subject project and authorized the advertisement
of bids for said work. This project will be funded by Assessment
District 85-1, Assessment District 86-2, and The Irvine Company.
DISCUSSION:
Five sealed bids were received and opened at i0:00 a.m. on September 12,
1989 and are summarized as follows:
1. Sully-Miller Contracting Company, Orange ............ $492,655.85
2. Vernon Paving Company, Anaheim ...................... $498,188.40
3. R. J. Noble Company, Orange ......................... $521,635.00
4. Industrial Asphalt, Irwindale ....................... $541,594.53
5. All American Asphalt, Corona ........................ $558,656.38
~s~.~c co~c~.~. ~v~.~.~ ov~.~', ~.~s~ ~s?x.
SEPTEMBER 12, 1989
PAGE 2
The low bid is 5.8% under the engineer's estimate of $523,000.00.
It is anticipated that construction will start in early October and be
completed in November.
Bob Ledendecker Jeff Chen
Director of Public Works/City Engineer Assistant Civil Engineer