HomeMy WebLinkAboutRPT 6 VANDENBERG WELL 10-16-89~; 'i:~ ~:.~ '~?'t, !~ ~ ~,.l ~ RE PORTS
.,_
DATE: OC~OB~ 12 ~ 1989
TO:
FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
VANDENBERG LANE WATER WELL STATUS REPORT
RECOMMENDATION:
Receive and file.
BACKGROUND:
The City Council at their meeting of October 2, 1989 requested an update
on the status of the Vandenberg Lane water well project. The proposed
location of this well site is on the northerly side of Vandenberg Lane
adjacent to and westerly of the Orange County Flood Control Channel
(Facility Fl2).
The well location is on property whiCh is currently under development as
a a retail commercial center and an office complex. During the plan
approval stage, staff has communicated with the developer regarding the
City acquiring a parcel of land for the' well development project and the
development has been designed so that the well improvements would have
minimum impacts to the development.
Following is a tentative schedule for the well project:
Finalization of parcel size and access easements
for well site Sept -Nov 1989
Acquisition of parcel/easements .................... Dec.'89-Jan.'90
Design of well development/well casing ............. Dec.'89-Mar.'90
Advertise, award, construct well development/
well casing project April- July '90
Design wellhead facility ........................... June -July '90
Advertise, award, construct wellhead facility* ..... July -Oct. '90
* The scheduling of this phase will be dependent upon when the developer
commences and completes the work for the enclosure of the Fl2 Flood
Control facility.
Bob Ledendecker
Director of Public Works/City Engineer
BL:mv