HomeMy WebLinkAboutOB 3 200 EL CAMINO RPT 11-06-89TO: FROM: SUBJECT: WILLIAM A. HUSTON, CITY MANAGER CHRISTINE SHINGLETON, DIRECTOR OF COMMUNITY DEVELOPMENT STATUS REPORT - 200 EL CAMINO RECOMMENDATION It is recommended that'the City Council authorize staff to obtain at least three demolition bids and order the demolition of a fire damaged structure by the lowest bidder as soon as possible and appropriate a maximum of $30,000 from general fund reserve for said work. BACKGROUND Staff have previously recommended deferring demolition of the fire damaged substandard structure at 200 E1 Camino Real to permit an additional effort at contacting the owner, representative of the owner and financial lender on the property based 6n advice of the- City Attorney. Unfortunately, over the last thirty days there have been no responses or any effort to get the premises cleared. Numerous site inspections of the broperty as well as additional complaints have been received over the last several weeks. Staff is concerned at this time that it is becoming more difficult to keep the site secured and it is becoming an attraction for trespassers which poses a significant public health and safety hazard. Staff have contacted several demolition contractors for preliminary demolition estimates. Estimated costs for this demolition could range from $20,000 to $30,000. It is requested that the City Council authorize staff to obtain at least three demolition propOsals and authorize Staff to order the demolition to the lowest bidder as soon as possible. Once the work is completed and costs finalized, the City would hold a public hearing and could assess and recover all costs incurred through a lien or assessment against the property. · · CAS: kbc