HomeMy WebLinkAboutCC 14 PROJECT 900027 08-01-88 NO. 14
DATE:" '"' JULY 27, 1988 Inter-Coin
TO: WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AUTHORIZATION TO ADVERTISE FOR BIDS FOR LOWER PETERS CANYON
RETARDING BASIN (FACILITY F06B01~ AND APPURTENANT FACILITIES,
~ PROJECT NO. 900027~ ASSESSMENT DISTRICT NO. 86-2
RECOMME ~DATION:
It is recommended that the City Council adopt a resolution authorizing
adve£tising for bids for this project.
BACKGROUND:
A key. element in development of the Tustin Ranch area north of Irvine
Boulevard is the construction of this facility. This project consists
of an earth dam, a holding reservoir, inlet works and outlet works.
The project will receive peak storm waters and release them in a
controlled manner at a much lower rate of flow. The facility is
located in the lower portion of the proposed regional park. The plans
have been reviewed by the State Division of Safety of Dams and by the
Orange County Flood Control District-. The latter agency will take uv=~
and maintain the project after construction is completed.
The estimated cost is $4,947,000 and will be financed with Assessment
District 86-2 bond funds. The proposed schedule shown below is subject
to timely receipt of the state permit.
Bid authorization
1st legal advertisement
2nd legal advertisement
Open bids
Award contract
Start construction
Finish construction
8-01-88
8-11-88
8-18-88
9-13-88
9-19-88
10-17-88
4-17-89
An agreement among the City of Tustin, Orange County Flood Control
District (OCFCD) and The Irvine Company (TIC) will be scheduled for
City Council approval on August 15. This will spell out the
obligations of each party which include the City to construct the
facility, OCFCD to maintain and operate it and TIC to proyide th~
rights of way and easements.
Bob Le-dendecker
Director Public Works/City Engineer
Ron ld E.
Engineering Se~ices Manager
1
2
5
6
?
9
10
11
12
13
15
16
19
20
21
25
26
27
25
RESOLUTION NO. 88-89
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUSTIN, CALIFORNIA, APPROVING PLANS AND
SPECIFICATIONS FOR CONSTRUCTION OF LOWER PETERS
CANYON RETARDING BASIN (FACILITY F06 B01)
AND APPURTENANT FACILITIES, PROJECT NO. 900027,
ASSESSMENT DISTRICT NO. 86-2
WHEREAS it is the intention of the City Council of the
City of Tustin, California to contract construction of Lower
Peters Canyon Retarding Basin (Facility F06 B01) and Appurtenant
Facilities, Project No. 900027, Assessment District
No. 86-2; and
WHEREAS, the City Engineer has presented plans and
specifications for the construction of said work;
NOW THEREFORE, BE IT RESOLVED that the plans and
specifications presented by the City Engineer be and are hereby
approved as the plans and specifications for:
Construction of Lower Peters Canyon Retardi~g Eaji.,
(Facility F06 B01) and Appurtenant Facilities, Project
No. 900027, Assessment District No. 86-2
BE IT FURTHER RESOLVED that the City Clerk is hereby
authorized and directed to advertise as required by law for the
receipt of sealed bids or proposals for the doing of the work
specified in the aforesaid plans and specifications;
BE IT FURTHER RESOLVED that this project is
covered by a previous Environmental Impact Report (EIR #85-2)
for the East Tustin Specific Plan and no additional
documentation is required.
PASSED AND ADOPTED at a regular meeting of the City
Council of the City of Tustin, held on the day. of
, 1988.
ATTEST:
RONALD HOESTEREY
Mayor
MARY E. WYNN
City Clerk