HomeMy WebLinkAboutCC 8 TRAFFIC SIG MOD 10-03-88'" ..... - CONSENT CALENDAR
TO:
WI55IAM HUSTON, CITY MANAGER
I=ROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS
SUBJECT: TRAFFIC SIGNAL MODIFICATION AT WALNUT AVENUE AND
CHERRYWOOD LANE (PROJECT NO. 700086, FILE NO. 2382)
RECOMMENDATION:
It is recommended that City Council, at their meeting of October 3,
1988, adopt the attached resolution accepting said work authorizing the
recordation of the Notice of Completion.
Assuming no claims or stop payment notices are filed, it is further
recommended that 30 days after the date of recordation of the Notice of
Completion, that the Council authorize payment of the final 10%
retention amount of $935.00. This amount together with previous
payments of $8,415.00 represents 100% of the final contract amount.
~ACKGROUND:
In April, I988, the City Council awarded the contract to Baxter-Griffin
Company, Inc. in the amount of $9,350. This pr0j ect encompassed
construction of traffic signal modifications for adding left turn
phasing for traffic on Walnut Avenue turning left onto Cherrywood Lane.
The final contract amount on this project was $9,350. Ail work has
been completed as per the requirements of the plans and specifications
and to the satisfaction of the Public Works Department.
Bob Ledendecker
Director Public Works/City Engineer
BL:JC:bf
Attachment
CC: City Clerk
Finance Director
Street Maintenance Superintendent
Jeff Chen
Assistant Civil Engineer
1
2
3
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
2O
21
22
23
24
25
26
27
28
RESOLUTION NO. 88-111
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUSTIN ACCEPTING WORKS OF IMPROVEMENT'AND
AUTHORIZING RECORDATION OF NOTICE OF COMPLETION
FOR CONSTRUCTION OF TRAFFIC SIGNAL MODIFICATIONS
AT WALNUT AVENUE AND CHERRYWOOD LANE
WHEREAS, Baxter-Griffin Company, Inc., having a contract
with the City of Tustin to construct the hereinafter
described public works and improvements; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinafter more
particularly described in accordance with the provisions of
the contract documents and the notice of completion, and
acceptance of said public work and improvement should be
filed and payment of the balance due said contract authorized
in accordance with the contract documents.
NOW THEREFORE, BE IT RESOLVED by the City Council of the
City of Tustin that said public work and improvement be, and
the same is 'hereby accepted. Said public work and
improvement is more particularly described as follows:
Construction of traffic signal modifications for adding
left turn phasing for traffic on Walnut Avenue turning
left onto Cherrywood Lane.
AND BE IT FURTHER RESOLVED that the City Engineer of the
City of Tustin be and is hereby authorized to execute and
file a notice of completion and acceptance of said public
work and improvement described herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City
Council of the City of Tustin on the day of
1988.
ATTEST:
Mayor
City Clerk