HomeMy WebLinkAboutNB 4 CONST SIDEWALKS 11-07-88 .~:.~.~ ~.~ - ~ -- NEW BUSINESS
OATE: OCTOBER 27, 1988 ~ ........
TO:
WILLIAM HUSTON,.CITY MANAGER
FROM: . PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT FOR CONSTRUCTION OF SIDEWALKS AND
LANDSCAPING, TUSTIN RANCH, PHASE II
RECOMMENDATION:
It is recommended that the City Council award the contract to Tracy
and Haigh, Inc., Rancho Santa Margarita, in the amount of $896,274.22.
BACKGROUND:
Four bids were received at the bid opening on October 25, 1988 which
are summarized as follows:
Tracy and Haigh
Valley Crest Landscape
Allied Sprinkler
Moulder Bros.
..
$ 896,274.22
$ 928,648.38
$1,057,959.00
$1,070,641.46
The low bid is 16.5% below the engineer's estimate of $1,074,417.
sidewalk construction and median landscaping will be financed with
Assessment District 85-1 bond funds in the amount of $331,479.22 and
the perimeter landscaping will be financed by The Irvine Company in
the amount of $564,795.00.
The
It is anticipated that construction will begin about November 21, 1988
with construction completed in March 1989.
Bob Ledendecker Jerry~Ottes-oh
Director of Public Works/City Engineer Associate Civil Engineer
BL:JO:mv