HomeMy WebLinkAboutNB 4 CONST OF ROAD 11-21-88 NEW BUSINESS
~, ,?'";-'"~,~ ~ ~ ~ ,~,,, ,.~ ~ NO. 4 '
:,-.,, .... //-
DATE~ RO~D~BD~ -~5~ 1988
TO: WILLIAM HUSTON, CITY MANAGER
·
'FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJ£CT: AWARD OF CONTRACT FOR CONSTRUCTION OF JAMBOREE ROAD BETWEEN
IRVINE BOULEVARD AND TUSTIN RANCH ROAD
RECOMMENDATION:
It is recommended that the City Council award a contract to Sully
Miller Contracting Company in the amount of $4,309,315.55 for the
above-referenced project.
BACKGROUND:
Bids were opened November 10 for the above-referenced project and six
bids were received as follows:
Sully Miller, Orange_. .......... [ .......[..[ $4,309,315.55
Silveri & LeBouef, Anaheim .......... ' . $4,355,669.56
Amen Brothers, Inc., Covina ................ $4,486,971.90
·
Griffith Co., Santa Ana .................... $4,594,124.80
Blair Paving, Inc., Anaheim ................ $4,773,158.02
E. L. Yeager Co., Riverside ................ $4,886,119.00
The low bid by Sully Miller Contracting Company is 30% below the
engineer's estimate of $6,177,077. Sully Miller Company is well known
in this area and is now completing contracts for the City in the
Tustin Ranch area.
This improvement on Jamboree Road wilI include curbs, gutters, paving,
traffic signals, street lights, storm drains, and a bridge at Peters
Canyon channel. Funding will be with Assessment District 86-2 bond
funds.
Bob Ledendecker
Director of Public Works/City Engineer
Ronaid E. W~lVfo¢~
Engineering Ser~ces Manager
BL:REW:mv