FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
IMPLEMENTATION OF LEFT TURN PHASING AT WALNUT AVENUE AND
CHERRYWOOD LANE.
RECOMMENDATION:
That the Tustin City Council at their meeting of February 1, 1988
authorize a supplemental budget appropriation in the amount of $9,300.00
to the 1987-88 Budget for the implementation of left-turn phasing at the
intersection of Walnut Avenue at Cherrywood Lane.
BACKGROUND:
At their meeting of January 18, 1988, the City Council authorized the
implementation of protected left turn phasing at the intersection of
~alnut Avenue and Cherrywood Lane for the Walnut to Cherrywood
ovements.
Staff had indicated at that meeting that a supplemental budget
appropriation would be required to fund said work and would return to
the February 1, 1988 City Council meeting with a request for said
funding.
DISCUSSION:
The estimated construction cost for signal modification work to
accommodate said left-turn phasing is $7,500.00 will include two new
signal standards, additional signal indication heads~loop detection and
~odification to the traffic signal controller. In addition to this cost
it is estimated that the plan and specification preparation for said
~ork will be $1,800.00. The total estimated cost for this project is
$9,300.00.
Bob Ledendecker
Director Public Works/City Engineer
B.L: bf