HomeMy WebLinkAboutOB 2 CONCRETE MEDIAN 02-01-88TO:
WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJEOT: AUTHORIZATION TO ADVERTISE BIDS FOR EMBOSSED CONCRETE MEDIAN
PAVING IMPROVEMENTS (FILE NO. 2445A)
RECOMMENDATION:
Pleasure of the City Council.
BACKGROUND:
At their meeting of January 18, 1988, the Tustin City Council raised
some concerns with the proposed paving of certain median islands with
embossed concrete. These concerns centered around the loss of turf
and/or other landscaping within the median islands.
Staff was requested to provide photographs and a map indicating the
individual areas of proposed median paving. Each of the attached
photographs are cross-referenced to a vicinity map for identification.
DISCUSSION:
The proposed embossed paving consists of eleven locations as follows:
1. Fiwe locations which require the removal of existing
landscaping (areas 1, 2, 3, 4 and 5).
2. One location which requires the removal of asphalt
concrete paving (area 6) .
3. Five locations which are replacement areas for previously
placed embossed concrete that had to be removed for
maintenance of irrigation facilities (areas 7, 8, 9, 10 and ll) c
The following is a revised tentative schedule for the subject project:
City Council Determination
of Project Scope
Authorization to Advertise Bids
First Legal Advertisement
Second Legal Advertisement
Open Bids
Contract Award
Commence Construction
Complete Construction
- - February 1, 1988
February 16, 1988
February 25, 1988
March 3, 1988
March 10, 1988
March 21, 1988
April 4, 1988
May 2, 1988
Bob Ledendecker
Department Public Works/City Engineer