HomeMy WebLinkAboutNB 1 STORM DR IMPROV 02-01-88DATE: JANUARY 26, 1988 ~,~~~F .......... I
TO:
FROM:
WILLIAMHUSTON,. CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT - SIERRA VISTA, KAREN WAY, JAN MARIE &
PANKEY WELL SITE STREET AND STORM DRAIN IMPROVEMENTS (#1245)
RECOMMENDATION:
It is recommended that the City Council at their regular council meeting
of February 1, 1988 award the contract for subject project to Elser
Construction of Yucaipa, California, in the amount of $219,505.00.
BACKGROUND:
On December 21, 1987, the City Council authorized the advertisement of
bids for the subject project.
DISCUSSION:
Sealed' bids were received and opened at 10:00 A.M. on Tuesday, JanUary
26, 1988 and are summarized below:
1. Elser Construction, Yucaipa ................... $219,505.00
2. R.L.T. Construction, Santa Ana ................
3. Larry Pennuri, Baldwin Park ...................
4. Spear Pipeline, Orange
5. Jana Contracting, Buena Park
6. Gillespie Contruction, Costa Mesa .............
7. John T. Malloy ................................
8. Colich & Son, Gardena .........................
·
9. Clayton Engineering, Laguna Hills .............
222,478.76
224,554.50
225,000.50
225,149.00
234,050.00
243,894.75
260,712.50
276,729.80
The low bid is 10.8% over the Engineer's Estimate. As this project is
partially funded with HCDA monies, the City's share is $60,930.00 and
HCDA share is $158,575.00.
Construction is anticipated to be completed by June 1, 1988.
Bob Ledendecker
Director of Public Works/City Engineer
BL/mv
Tim Tucker
Assistant Civil Engineer