HomeMy WebLinkAboutNB 2 WTR MAIN IMPROV 03-07-88 NEW BUSINESS
· ,o.
DATE: lv~._RCH 1, 1988 \~.~~?,/ .... ---, v,~,,.-.~,~ I
TO.",
WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT FOR WATER MAIN IMPROVEMENTS ON MYRTLE AVENUE,
"C" STREET, KENNETH DRIVE AND KEITH PLACE
RECOMMENDATION:
It is recommended that the City Council, at their meeting Of March 7,
1988, award the contract for %nbject project to R.L.T. Construction,
Inc. of Santa Ana, California, in the amount of $160,797.50.
BACKGROUND'.
On February 1, 1988, the City Council approved plans and specifications
and authorized the advertisement for bids for the subject project.
-rlISCUSSION:
~led-bids for this work were opened on March 1, 1988 at 11:00 a.m.
were received as follows:
R.L.T. Construction, Santa Ana
Changing Times Enterprises, Santa Ana
Simich Construction, Walnut ..............
Marnatt Construction, Orange .........
Petar Artukovich Construction, Whittier
Spear Pipeline Construction, Orange ---
Jana Contracting Corp., Buena Park
R & L Sewers, Inc., Paramount ......
Brkich Bros. Construction, E1 Monte
Majich Bros. Construction, Pasadena
$160,797.50
$169,516.00
$186,501.00
.... $189,706.50
$193,891.00
--- $195,999.95
-- $199,321.00
·
- $204,608.20
- $216,657.00
$218,069.00
The low bid is $160,797.50, or about 28% below the Engineer's Estimate
of $224,465.00. There is presently $228,000.00 allocated in the FY
I987-88 budget for this project.
~b Ledendecker
.~ector of Public Works/City Engineer
~ ~L:SW:mv
Steve Worrall
Assistant Civil Engineer