HomeMy WebLinkAboutRPT 7 JAMBOREE STATUS 3-7-88TO:
WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJEOT: JAMBOREE ROAD STATUS REPORT UPDATE
This status report will cover that portion of Jamboree Road from
Barranca Road on the south to Chapman Avenue (relocated) on the north.
It will be divided into five segments as follows:
1. Segment one between Barranca Road and Edinger Street
2. Segment two between Edinger Street and the I-5 Freeway
3. Segment three-being the Jamboree Road/I-5 Interchange
4. Segment four between the I-5 Freeway and Irvine Boulevard
5. Segment five between Irvine Boulevard and S~ntiago Canyon Road
(relocated in Orange). Also, referred to as the North-South Rd.
Each segment, one, three, four and five, will be contracted as a
separate contract and will be described in detail below. Segment two is
an existing roadway and was completed under two separate contracts in
1984 for the portion southerly of the A.T. & S.F. Railroad and in 1986
for the portion northerly of the railroad.
Segment one is a joint effort between The Irvine Company and the cities
of Irvine and Tustin. Total estimated project cost is $22,800,000 and
is proposed to be funded by the three agencies as follows: Irvine
Company - 36%, City of Irvine - 46% and City of Tustin - 18%. Tustin's
share is $4,104.000. This project cost includes right of way
acquisition, construction and relocation of the heavy lift operation to
Camp Pendelton from MCAS-Tustin. Following is a tentative project
schedule:
a. Certification of Environmental
Assessment Document ............. (COMPLETED)
b. Plans, specs, estimate to first plan check .................
12/87
c. Final approval of plans, specs and
estimate by Caltrans/FHWA .........
5/88
d. Completion Of burn pit/Moffett trenches
clean-up ...................
6/88
e. Advertise bids * ................ 8/88
JAMBOREE ROAD STATUS REPORT UPDATE
MARCH 2, 1988
Page 2
*Bid advertisement is contingent upon funding availability. As of this
date, no construction funds are available.
Seqment three is a project being designed and constructed by Caltrans
and consists of the total reconstruction of the existing Jamboree Road/
I-5 Interchange to a full movement partial cloverleaf interchange
facility. The tentative schedule for this project is:
a. Finalization of plans
by Caltrans ..............
In progress
b. Advertise bids ...............
6/88
c. Commence construction ...........
9/88
d. Complete construction ...........
9/89
,eqment four is being financed through funding provided by Assessment
District No. 85-1. The total estimated cost for this project is
$3,900,000. Following is the tentative schedule for this project:
a. Approval of plans, specs and estimate ..... (COMPLETED)
b. Award contract ................ (COMPLETED)
c. Commence construction ............
12/87
d. Complete construction ...........
6/88
Segment five will ultimately be financed through Assessment District
No. 86-2. In the interim until this Assessment District is finalized
and per agreement between the City and The Irvine Company, funding will
be provided by the Company for that portion of the project within
Tustin City limits. Tustin will be acting as the lead agency for both
the City of Orange and the County of Orange within their respective
areas. It is anticipated that this project will be constructed under
two separate major contracts; grading and drainage facilities, and
roadway improvements. The preliminary cost of this segment is
estimated at $30,000,000 and will provide for three southbound travel
lanes and two northbound travel lanes within the City of Tustin, and
two travel lanes in each direction within the City of Orange and County
of Orange. The project area within the limits of the unincorporated
County area are currently under annexation proceedings to the City of
trange which are scheduled for finalization in late February, 1988.
Plans and specifications are currently under preparation by Hunsaker
and Associates. Following is a tentative schedule for this segment:
JAMBOREE ROAD STATUS REPORT UPDATE
MARCH 2, 1988
Page 3
a. Circulation of EIR ............... (COMPLETED)
·
b. Public hearing/certification of EIR ...... (COMPLETED)
c. Plans, specs, estimate complete ....... .. 4/88
d. Commence grading/drainage construction .... 5/88
e. Complete grading/drainage construction .... 1/89
f. Commence roadway construction ......... 1/89
g. Complete roadway construction ......... 6/89
As schedules are revised, periodic updates of this report will be
furnished.
Bob Ledendecker
Director Public Works/City Engineer
BL:bf