HomeMy WebLinkAboutNew Business #1 6-15-87TO:
WILLIAM HUSTON, CITY MANAGER
FROM:
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT:
AWARD OF CONTRACT FOR MANUFACTURE AND DELIVERY OF REINFORCED CONCRETE
PIPE FOR TUSTIN RANCH PROJECT, A.D.No. 85-1
·
RECOMMENDATION:
For the City Council meeting of June 15, 1987.
It is recommended that the City Council award the contract to Hydro Conduit Corporation
Corona, in the amount of $703,435.25 for the subject project.
BACKGROUND:
Three bids were received at the bid opening on June 2, 1987. They are summarized
as follows:
FIRM BID PRICE DELIVERY TIME
Hydro Conduit Corp.,Corona
$ 703,435.25
70 - 112 days
Ameron, Inc.,Monterey Park
768,522.53
98 - 133 days
United Concrete Pipe,
Baldwin Park
801,370.92
49 - 74 days
The low bid is 7.8% over the engineer's estimate of $652,761 which is within an
acceptable range. Hydro Conduit% delivery time also meets project schedule
requirements. Project funding is by Assessment District 85-1 bond proceeds
($694,798.68) and. Irvine Company funds ($8,636.57).
Bob Ledendecker
Director of Public Works/CityEngineer
Ronald E. Wolford //
Engineering Servic~Fs Manager
BL:REW:jp