HomeMy WebLinkAboutNB 2 WTR MAIN IMPROV 04-04-88DATE:
TO:
WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT FOR WATER MAIN IMPROVEMENTS ON WALNUT STREET,
ORANGE STREET, PROSPECT AVENUE AND LOCKWOOD PARK PLACE
RECOMMENDATION:
It is recommended that the City Council, at their meeting of April 4,
1988, award the contract for subject project to Zagros Company of
Irvine, California, in the amount of $146,509.50.
BACKGROUND:
On February 16, 1988, the City Council approved plans and specifications
and authorized the advertisement for bids for the subject project.
ISCUSSION:
aaled bids for this work were opened on March 29, 1988 at 11:00 A.M.
and were received as follows:
Zagros Company, Irvine
R & L Sewers Inc., Paramount
A & L Construction, Costa Mesa
Janna Contracting Corp., Buena Park
Elser Constructors, Yucaipa
Bobco Construction, La Habra
Spear Pipeline Construction, Orange
Coast Pipeline Corp., Villa Park
Changing Times Enterprises, Buena Park
John Malloy Inc., Los Angeles
$146,509.50
$155,463.2!5
$161,267.50
$166,391.O0
$168,584.O0
$169,337.5.0 .
$169,503.70
$177,902.50
$184,229.50
$196,015.0!0
The low bid is $146,509.50, or about 24% below the Engineer's estimate
of $194,000.00. There is presently $208,000. allocated in the FY
1987-88 budget for this project.
db Ledendecker
irector Public Works/City Engineer
BL:SW:bf
Steve Worrall
Assistant Civil Engineer