HomeMy WebLinkAboutNB 1 WTR MAIN IMPROV 04-18-88DATE:
APRIL 12, 1988
NEW BUSINESS
4-18-88
TO:
FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
AWARD OF CONTRACT FOR WATER MAIN IMPROVEMENTS ON EDINGER
AVENUE, WINDSOR LANE, CATALINA DRIVE, DEL REY DRIVE, AND
LA BELLA DRIVE, PROJECT NO. 600058.
RECOMMENDATION:
It is recommended that the City Council, at their meeting of April 18,
1988, award the contract for subject project to Coast Pipeline
Corporation of Laguna Hill, California, in the amount of $163,011.61.
BACKGROUND:
On March 7, 1988, the City Council approved plans and specifications
and authorized the advertisement for bids for the subject project.
]ISCUSSION:
Sealed bids for this work were opened on April 12, 1988 at 11:00 A.M.
and were received as follows:
Coastline Construction, Laguna Hills
Spear Pipeline, Orange
A & L Construction Co., Costa Mesa
Elser Constructors, Yucaipa
Murray Company, Rancho Dominguez
RLT Construction, Santa Ana
simich Construction, Walnut
Coast Pipeline, Orange
Marie M. Thomas Construction, Hemet
R & L Sewer, Paramount
Majich Bros., Pasadena
Ruiz Engineering, Long Beach
John T. Malloy
$163.011.61
168.004.50
171 695.00
186.307.50
191 775.00
199 960.00
203 669.00
204,625.00
206,319.00
207,015.00
207,725.00
220,320.50
242,200.00
The low bid is $163,011.61, or about 26% below the Engineer's
estimate of $221,400.00. There is presently $221,500. allocated in
the FY 1987-88 budget for this project.
Bob Ledendecker
Director Public Works/city Engineer
BL:SW:bf
Steve Worrall
Assistant Civil Engineer