HomeMy WebLinkAboutRPT 3 S.D. PIPELINE INST 5-2-88DATE: APRIL 26, 1988 REPORTS NO. 3 5-2-88 Inter- Com TO: WILLIAM HUSTON, CITY MANAGER FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION SUBJEGT: STATUS REPORT - SAN DIEGO PIPELINE INSTALLATION Installation of all pipeline facilities have been completed and the pressurized testing of both pipelines are being completed. Staff has requested that all final pavement replacement on the trench excavations be delayed until such time the pressure testing is completed and accepted. This one-time final pavement replacement operation will provide a more uniform riding surface. It is anticipated that the final paving operation will commence on or about May 2, 1988 and will be completed in approximately seven working days. This final paving operation will consist of grinding the xisting pavement edge adjacent to the existing trench and resurfacing co the original street elevations. Additionally, all pavement markings will be restored to their original condition. Bob Ledendecker Director of Public Works/city Engineer BL:mv