TO: WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJEGT: STATUS REPORT - SAN DIEGO PIPELINE INSTALLATION
Installation of all pipeline facilities have been completed and the
pressurized testing of both pipelines are being completed.
Staff has requested that all final pavement replacement on the trench
excavations be delayed until such time the pressure testing is
completed and accepted. This one-time final pavement replacement
operation will provide a more uniform riding surface.
It is anticipated that the final paving operation will commence on or
about May 2, 1988 and will be completed in approximately seven working
days. This final paving operation will consist of grinding the
xisting pavement edge adjacent to the existing trench and resurfacing
co the original street elevations. Additionally, all pavement markings
will be restored to their original condition.