WILLIAM HUSTON, CITY MAI~AGER
PUBLIC WORKS DEPARTNEI~r/ENGINEE'RING DIVISION
AWARD OF CONTRACT FOR IMPROVEMENTS-ON TUSTIN RANCH ROAD AND NY¢ORD
ROAD, AD 85-1
RECOMMENDATION:
It is recommended that the 'City Council award the contract to the low bidder,
Sully Miller Contracting Co., Orange, in the amount of $1,998,197.50 for subject
project.
BACKGROUND:
Four bids were received at the bid opening On July 14. They are summarized as
follows:
Sully Miller, Orange
Blair Paving, Anaheim
Aman Bros., Covina
Griffith Company, Santa Ana
$1,998,197.50
$2,109,331.73
$2,253,643.20
$2,287,370.05
The low bid is 19% under the engineers' estimate of $2,477,723.75. This project
is financed with assessment district bond funds and will provide *street
improvements and utilities for Tustin Ranch Road between Bryan avenue and. Irvine
Boulevard and for Myford Road (New Myford) between E1 Camino Real and Irvine
Boulevard.
Bob Ledendecker
Director of Public Works/City Engineer
BL/REW/lg
g' eering Servi~Manager