NEWPORT AVENUE CROSSING
RECOMMENDATION:
That the City Council adopt the attached resolution which finds that
additional environmental studies are not required in order for the City to
apply to the State Public Utilities Commission (PUC) for a grade crossing on
Newport Avenue.
BACKGROUND:
In 1983 the City Council certified an EIR and submitted an application to the
PUC for a grade crossing at Newport Avenue. The application was withdrawn by
the City as a result of its decision to evaluate the feasibility of a grade-
separated crossing. The evaluation demonstrated that a grade-separated
crossing is not feasible. The City Council then directed staff to again make
application to the PUC for authorization to re-establish a grade crossing on
Newport Avenue. Staff has prepared the application and is ready to file it
subject to a determination by the City Council that the EIR certified in 1983
is adequate for the current application. As indicated in the resolution, no
subsequent changes are proposed in the project which would require additional
environmental studies.
William A. Huston
City Manager
WAH:jh
Attachment: Resolution No. 86-98
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
271
28
RESOLUTION NO. 86-98
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
TUSTIN, CALIFORNIA, FINDING THAT NO CHANGES
HAVE OCCURRED WITH RESPECT TO THE PROPOSED
NEWPORT AVENUE GRADE CROSSING
WHEREAS, by application dated April ~ , 1984, the City of
Tustin applied to the California Public Utilities Commission to
construct a grade crossing across the Right-of-Way of the Atchison,
Topeka and Santa Fe Railway Company on Newport Avenue; and
WHEREAS, that application was withdrawn by letter dated
September 2, 1985, in order that the City might evaluate a grade
separation at said site; and
WHEREAS, the City later determined that a grade separation
was not feasible and that it wished to reapply for permission to
establish a grade crossing; and
WHEREAS, by Resolution No. 83-68, passed and adopted by the
City Council on October 5, 1983, the City Council certified Final
EIR 83-1 on said project; and
WHEREAS, the City Council has reviewed said EIR in order to
determine whether any additional' EIR need be prepared.
NOW, THEREFORE, the City Council of the City of Tustin,
California, does hereby RESOLVE as follows:
~ 1: No subsequent changes are proposed in the
project which will require important revisions of the previous EIR
due to the involvement of new significant environmental impacts not
considered previously.
Section 2: No substantial changes have occurred with
respect to the circumstances under which the project is undertaken,
which would require important revisions in the EIR due to the
involvement of new significant environmental impacts not covered in
the EIR.
Section 3: Based on the above, no further EIR need be
prepared.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED AND ADOPTED at a regular meeting of the City Council
of the City of Tustin, California, held this ~ day of
, 1986.
Mayor
ATTEST:
City Clerk
JGR:LSL :pj (62)