AUGUST 31,, 1987
TO: "
WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT FOR IMPROVEMENTS ON IRVINE BLVD., BRYAN AVE. AND
BROWNING AVE., ASSESSMENT DISTRICT NO. 85-1
RECOMMENDATION:
That the Tustin City Council at their meeting of September 8, 1987 award the
contract of street/utility improvements on Irvine Blvd., Bryan Ave. and Browning
Ave. to the low bidder, Sully-Miller Contracting Company of Orange, in the amount
of $2,387,211.62.
BACKGROUND:
On July 20, lg87, the Tustin City Council approved the plans and specifications
for the subject street improvement/utility project and authorized the
advertisement of bids for said work. This project is a part of East Tustin
Assessment District No. 85-1 and will be funded by said Assessment District.
DISCUSSION:
Three sealed bids were received and opened at 10:00 a.m. oh August 27, 1987 and
are sunmnarized as follows:
Sully-Miller Contracting Company, Orange ........................... $2,387,211.62
Griffith Company, Santa Ana ........... ' ............................. $2,650,121.85
Blair Paving Company, Anaheim ...................................... $2,854,855.29
The low bid is 10.6% under the engineer's estimate of $2,670,577.95. A detailed
bid item summary is attached for the City Council's information.
Sully-Miller Contracting Company was the low bidder on two adjacent street
improvement projects within the Assessment District area and was also awarded that
contract.
Director of Public Works, City Engineer
BL/lg
Attachment