HomeMy WebLinkAboutRDA ST. LGHTNG "C" ST. 02-17-87DATE: FEBRUARY 9, 1987
REDEVELOPMENT AGENCY
NO. 5
2-17-87
Inter- Corn
TO:
FROM:
SU BJ ECT:
WILLIAM HUSTON, EXECUTIVE DIRECTOR
TUSTIN CO~NITY REDEVELOPMENT AGENCY
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUPPLEHENTAL BUDGET APPROPRIATION - STREET LIGHTING ALONG "C' STREET
RECOMMENDATION:
For the Tustin Community Redevelopment Agency meeting of February 17, 1987.
Authorize supplement appropriation in the amount of $6,950.00 to the Tustin
Community Redevelopment Agency 1986-87 Budget for street light installation along
"C" Street between Main Street and Third Street, and authorize City staff to
administrate all contracts for said installation.
BACKGROUND.:
At their meeting of February 2, 1987, the City Council reviewed the feasibility of
installing street lighting along "C" Street between Main Street and Third Street.
Their final action was to install three street lights at an estimated cost of
$6,950.00.
DISCUSSION:
The City Council also discussed the feasibility of funding this street light
installation with Redevelopment Agency funding and concluded that Agency funding
should be utilized.
The requested action for the Agency is to authorize a supplemental appropriation
in the amount of $6,950.00 to the Tustin Community Redevelopment Agency (Town
Center Project Area) 1986-87 Budget, and authorize City staff to administrate all
contracts for said installation.
Bob Ledendecker
Director of Public Work~/City Engineer