HomeMy WebLinkAboutNB 8 PROJ M-M016(002) 04-07-86NEW BUSINESS
NO. 8
4-7-86
DATE:
MARCH 31, 1986
Inter'- Com
TO: THRU:
FROM:
WILLIAM HUSTON, CITY MANAGER
BOB LEDENDECKER, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
DALE A. WICK, ASSISTANT CITY ENGINEER
SUBJECT: AWARD OF CONTRACT FOR NEWPORT AVENUE FAU PROJECT M-M016(O02)
RECOMMENDATION:
It is recommended that the City Council, at their meeting of April 7, 1986, award
the contract for subject project to Steiny and Company Inc. of Fullerton,
California, in the amount of $188,714.00.
BACKGROUND:
Subject project encompasses construction of a new traffic signal at the
intersection of Newport and Sycamore and modifications to the signals at Newport
Avenue and Walnut, McFadden and Mitchell. In addition, these signals will be
interconnected by utilization of a time base coordination system.
Sealed bids'for this work were opened at 10:00 a.m. on March 21, 1986 and we6e
received as follows:
Contractor Business Location Bid
Steiny and Co, Inc.
Moore Electrical Contracting
DBX, Inc.
Baxter-Griffin Co. Inc.
Fullerton, CA
Brea, CA
Temeoul a, CA
Stanton, CA
$188,714.00
189,800.00
202,222.00
730,000.00
The low bid is $5,914.00 or 3.24% over the engineer's estimate of $182,800.00.
This is a Federal Aid Urba6 Project and the City and Federal share of this project
is as tabulated below:
Cost Based on Low Bid *Budgeted Amount
Federal Funds $162,295.00
City Funds 26,419.00
Totals - $188 714 O0
$201,200.00
32,800.00
$234,000.00
*Budgeted amount also includes design and construction engineering costs of which
$10,000.00 has been expended to date for design engineering.
The contractor has met all Federal requirements and CalTrans has given the City
authorization to award the contract to Steiny and Company Inc.
MARCH 31, 1986
PAGE 2
Attached, for the City Council's information, is a tabulation of all bids
received.
Dale A. Wick
Assistant City Engineer
DAW:jr