HomeMy WebLinkAboutOB 3 TOLL RD FEASIBLTY 06-16-86 OLD BUSINESS
NO. 3
DATE: JUNE 11, 1986
TO:
FROM:
SUBJECT:
WILLIAN HUSTON, CITY MANAGER
PUBLIC gORKS DEPARTMENT/ENGINEERING DIVISION
FOOlllILL/EASTERN/I-5 BOI-FLENECK ANN_YSIS
AND TOLL ROAD FEASIBILITY STUDY
RECOMMENDATION:
For the City Council meeting of June 16, 1986.
Authorize staff to respond to the Orange County Transportation Commission per
comments/concerns outlined in the attached letter dated June 17, 1986.
BACKGROUND:
The Orange County Transportation Commission (OCTC) is acting as the lead agency on
the subject feasibility study and has conducted on-going public participation
meetings, Policy Advisory Committee meetings and Technical Advisory Committee
meetings.
At the most recent public participation meeting held on Wednesday evening, June 4,
1986, the findings of the Foothill/Eastern/I-5 Bottleneck Analysis and the Toll
Road Feasibility Study for the Foothill/Eastern Transportation Corridors were
disseminated and discussed with the public. A copy of these findings as well as
the Draft Executive Summary for the Foothill/Eastern/I-5 Bottleneck Analysis is
attached for-information.
As noted in the attachment, the Bottleneck Study area is bounded by Route 55 on
the west, Route 91 on the north, Eastern Transportation Corridor on the east and
the Santa Ana (I-5) Freeway on the south. Seven agencies are located within o~
are immediately adjacent td the study area as follows:
Anaheim Santa Ana
County of Orange Tustin
Irvine Villa Park
Orange
DISCUSSION:
Most of the emphasis on this study, to date, has been focused towards the
Bottleneck portion of the study. Consequently, this staff report will deal
primarily with the Bottleneck Analysis portion of the study.
JUNE 11, 1986
PAGE 2
There are four major categories of alternatives being studied:
1. MPAH baseline alternative (no project).
2. Freeway connector alternatives.
3. Arterial improvement alternatives.
4. Regional freeway system alternatives.
Each of the alternatives other than the no project alternative has subalternitive
variations which are discussed in the Draft Executive Summary document.
The "No Project" Alternative will adversely impact Tustin with increased
traffic/congestion on the existing arterial system as well as the I-5 and Route 55
freeways that traverse 'through Tustin corporate limits. This alternative could
also have adverse effects on the adjoining communities of Irvine, Santa Aha and
unincorporated County areas.
There are five variations of the Freeway Connector Alternatives, 2A, 2B, 2C, 2D
and 2E. Three of these Alternatives, 2C, 2D and 2E, appear to provide the
greatest degree of relief to congestion within the Bottleneck area. Alternative
2C and 2D provide the most direct connection between the Foothill Corridor and
Route 22 (Garden Grove Freeway) terminus. Alternative 2C/2D impacts the East
Tustin Specific Plan area just northerly of the Foothill Blvd. extension area~ and
Alternative 2E impacts a larger area as it traverses westerly (diagonally) across
the East Tustin Specific Plan area just northerly of the proposed golf course.
Both of these alternatives would impact the East Tustin Specific Plan.
The arterial alternative consists of six east-west arterial highways.
Alternatives 3C, 3D, 3E and 3F all directly affect the City of Tustin. It is
staffs viewpoint that the. advantages/disadvantages have not been adequately
addressed in certain areas of the preliminary evaluation. It does not appear that
Irvine Blvd. has been adequately evaluated with respect to right of way and
construction requirements between Newport Avenue and the Route 55 Freeway.
Additionally, this alternative does not appear to include any Route 55 Freeway
widening costs to accommodate the increased traffic flows from the arterial
system.
Alternative 4 consists of two subalternatives which involve the I-5'and Route 55
Freeways between the Eastern Corridor Interchange on I-5 and the Route 22
Interchange on Route 55, and an extension of the Route 57 Freeway to the San Diego
(I-405) Freeway.
The expansion of the I-5 and Route 55 Freeways would provide additional traffic
lanes by constructing an elevated transitway for carpools, buses and other
high-occupancy vehicles (H.O.V.). This particular alternative would clearly
impact the existing community of Tustin and Santa Ana that are immediately
adjacent to the freeways. In areas along I-5 such as Tustin Ranch Road, Red Hill
Avenue and Newport Avenue, the elevated transitway would be a three level
structure above existing ground. Along Route 55, the elevated transitway would be
one level above existing ground at First Street, Irvine Boulevard and Seventeenth
Street. At Santa Clara and Fairhaven Avenue the elevated transitway would be two
levels above existing ground. These elevated structures would definitely have an
adverse impact to adjoining residences and businesses.
· JUNE 11, 1986
PAGE 3
One of the major factors to be considered prior to finalization of this analysis
is the final disposition of both the Eastern Transportation Corridor (ETC) Study
and the Foothill Transportation Corridor (FTC) Study. Major new location options
have been added to the ETC Study which could include a shift to the east so as to
connect the ETC to SR 133 (Laguna Freeway). Additionally, modifications to the
westerly portion of the FTC are also under consideration.
The Orange County Transportation Commission Study has identified two scenarios
pertaining to ultimate recommendations as follows:
Scenario I
That the current County Master Plan of Arterial Highways
remains the same and without major change in ETC or FTC
locations, capacity and connection, and that demographic
assumptions remain consistent with current general
plans.
Scenario II -
That the current County Master Plan of Arterial Highways
is modified to relocate the ETC or FTC from their presently
proposed locations.
Under Scenario I, the study recommends the following alternatives be retained for
further consideration:
I - MPAH baseline (no project)
2C - Foothill, depressed
2D - Foothill, partial tunnel
2E - La Colina
3C - Seventeenth St./La Colina Dr.
3D - Irvine Blvd.
3F - Moulton Parkway
4A - I-5/SR 55 improvements
4B - SR 57 extension to 1-405 and SR 73
Staff does not concur with this recommendation as follows:
e
Alternatives 2A and 2B should not be eliminated from the study.
Impacts associated with Alternatives 3C and 3D do not appear to
have been adequately addressed.
Community impacts associated with Alternative 4A do not appear
to have been adequately addressed.
Under Scenario II, the study indicates that it would be premature to either adopt
or eliminate Bottleneck alternatives until such time the final alignments for both
the ETC and FTC can be determined. Additionally, at this time, updated land use
assumptions in the northeastern portion of the study area (18,000 acres in Orange)
can be integrated into the study. It is anticipated that the ETC Study will be
completed on or about February, 1988.
JUNE 11, 1986
PAGE 4
Staff concurs with the study recommendation under Scenario II.
Staff has drafted a letter summarizing Tustin's concerns and recommendations for
each scenario and requests authorization by the City Council to forward this
letter to the OCTC staff. All comments regarding this study have been requested
no later than Wednesday, June 18, 1986.
On Monday, July 28, 1986, the Orange County Transportation Commission will receive
the final reports which will include all agency and public concerns as well as
consultant responses to each concern.
OCTC staff has scheduled a presentation to the City Council at the July 7, 1986
Council meeting. This presentation will provide a general overview of the study
which should last approximately twenty minutes plus any question/answer period.
Director of Public Works/City Engineer
BL:jm
Attachment
Department of Public Works/Engineering
dune 17, 1986
Ms. Sharon Greene, Project Manager
Orange County Transportation Commission
1055 No. Main Street
Suite 516
Santa Ana, CA 92701
RE: FOOll(ILL/EASTERN/I-5 BOI'I1.ENECK ~YSIS AJ~I) TOLL ROAI) FEASIBILITY STUDY
Dear Ms. Greene:
The City of Tustin has completed its review of the draft final report for the
Foothill/Eastern/I-5 Bottleneck Analysis and Toll Road Feasibility Study and will
generally outline below some of our continuing concerns as Well as concurrences
with the studies.
Foothill/Eastern/I-5 Bottleneck Analysis
Reference is made to my letter of April 8, 1986 outlining the City's concerns of
the preliminary alternatives evaluation. {Copy attached). Many of these concerns
are still existent with the completion of the final draft document.
Under Assumption I (Scenario I), the study recommgnds that Alternatives 2A and 2B
be eliminated from further study. We do not agree with the elimination of these
alternatives until such time they can be evaluated as a package solution with the
other Alternatives 3 and 4, as well as, ultimate land use plans in the
northeasterly portion of the study area (18,000 acres in Orange). The City does
not concur with the impacts associated with Alternatives 3C and 3D as outlined in
the study. If any requirements above a modified primary (six lanes) are required
along either Irvine Blvd. between Newport Ave. and SR 55 and along Seventeenth
St. between Prospect Ave. and SR 55, then the right of way cost/acquisitions do
not appear to be adequately addressed as well as other community impacts. The
City is opposed to Alternative 4A, as presented, due to the air quality, noise and
aesthetic impacts as outlined in the study.
Under Assumption II {Scenario II), the City is in concurrence with the study
findings that fihalization of the Bottleneck Analysis cannot be made until such
time the alignments for both the Eastern and Foothill Transportation Corridors
have been finalized.
300 Centennial Way · Tustin, California 92680 · (714) 544-8890
June 17, 1986
Page Two
Toll Road Feasibility Study
The City has no specific comments on this portion of the study, except that
depending on whether Assumption I or II in the Bottleneck Study is implemented
expanded studies for the Eastern Transportation Corridor Toll Road portion may be
required.
The City thanks the O.C.T.C. again for the continued opportunity to provide our
input/comments to these studies.
Very truly yours,
Bob Ledendecker
Director of Public Works/City Engineer
BL:jm
Attachment
Department of Public Works/Engineering
April 8, 1986
Ms, Sharon Greene, Project Manager
Orange County Transportation Commission
1055 No. Main Street
Suite 516
Santa Ana, CA 92701
RE: FOOTHILL/EASTERN/I-5 BOlq'LENECK ANALYSIS AND TOLL ROAO FEASIBILITY STUDY
Dear Ms. Greene:
The City of Tustin has completed its initial review of the findings of the
preliminary alternatives evaluation for the Bottleneck Analysis portion of the
subject Feasibility Study. Following is a general recap of the City's concerns
and comments of the various alternatives:
Alternative !
The "No Project" Alternative is unacceptable to the City in that the existing and
masterblanned arterials and freeways will not 'be adequate to accommodate the
projected traffic flows. In the event the "No Project" Alternative is to be
considered for implementation, it should be conditioned with land use growth
controls through the south County and airport areas.
Alternative 2
During the discussions at the public meeting in Orange on January 30, 1986, it was
stated that the direct freeway connections (2C, 2D, gE) would most likely require
eight lanes of roadway (four lanes each direction). The consultants should
address these potential lane requirements as they relate to the other Alternatives
3 and 4?' If these Alternatives, 3 and 4, do not accommodate the traffic capacity
needs as outlined in 2C, 2D and 2E, then this should be so documented in the
evaluation process.
Alternative 3
A quantitative amount of relief to traffic congestion should be indicated with the
implementation of this alternative on an arterial by arterial basis.
Additionally, the study team should address any additional impacts to other roads
adjacent to the indicated arterials.
300 Centennial Way ,. Tusti~ California 92680 · (714) 544-8890
April 8, lg86
Page Twa
On Alternative 3C does the cost estimate include the u~grade to major standards of
the existing segments of Seventeenth St. which are currently improved to primary
standards?
On Alternative 3D it appears that the cost estimate of $3-5 million does not
include right of way acquisition and roadway construction between Newport Avenue
and the Route 55 Freeway. The current right of way width for the majority of
Irvine Blvd. between Newport Ave. and Route 55 is 100 feet with a building setback
of 10 feet for most parcels. Any physical widening would adversely impact the
business community along this roadway with displacements.
The Arterial Alternative does not appear to include any upgrading of the Route 55
Freeway between the various arterial connections and the Route 22 Freeway.
Additionally, this alternative could increase traffic concentration along the
Route 55 Corridor and within the I-5/Rte. 55 interchange area.
A clarification would be helpful as to what the intent of this alternative is with
respect to utilizing all six arterials or any portion of the total.
Alternative 4
It is requested that the traffic capacity needs be clearly defined in this
alternative. In Alternative 2 the direct connectors 2C, 2D and 2E required eight
lanes. It appears that only four lanes on I-5 and two lanes on Route 55 could be
made available with this alternative.
In Alternatives 2A and 2B it was indicated that these alternatives do not relieve
the I-5 Bottleneck ~ue to the indirect route to the Rte. 55/Rte. 22 interchange
area. Alternative 4A requires approximately the same length of indirect route
from the interchange area of the Eastern/Foothill Transportation Corridors to
Rte. 55/Rte. 22 interchange area. As a result of this alternative, motorists
would tend to utilize the I-5 Freeway in lieu of the Foothill Transportation
Corridor which may impact larger areas of the I-5 Freeway.
The City thanks the O.C.T.C. for the opportunity to participate and comment on
this preliminary alternatives evaluation. Hopefully, the finalization of this
Feasibility Study will serve as a tool for all involved agencies to resolve one of
the most critical transportation needs within the County.
Very truly yours,
Director of Public Works/City Engineer
BL:jr
Prepared for
Orange Count. Transportation Commission
Executive Summary
I!
FOOTH ILL/EASTE RN / 1-5
BOTTLENECK ANALYSIS
GRUEN ASSOCIATES
Prcparcd for
Orange County Transportation Commission
Draft
Executive Summary
FOOTHILL/EASTERN/I-5
BOTTLENECK ANALYSIS
Prepared by
'GRUEN ASSOCIATES
In Association With
LSA, Endo Engineering,
Leighton and Associates, Inc.
and Shirley A. Montoya
May, 1986
FOOTHILL/EASTERN/I-5 BOTTLENECK ANALYSIS
EXECUTIVE SUMMARY
I INTRODUCTION
Rapid growth in Orange County has created urgent
transportation needs, including the need for major
improvements in the existing Santa Ana Freeway Corridor
and the need for development of the proposed new Foothill
and Eastern Transportation Corridors (FTC and ETC,
respectively). In response to these needs, local and
State agencies have focused attention over the past decade
on upgrading existing facilities and on possible new
highway routes. But concerns exist that a Bottleneck may
be developing in the I-5 Corridor in the area of
confluence with the new corridors.' To address these
concerns, the Orange County Transportation Co~[]~ission has
coordinated efforts with affected local agencies,
including the Orange County Environmental Management
Agency and the Cities of Orange, Tustin, Irvine, Villa
Park, Anaheim, Yorba Linda and Santa Ana to undertake a
study of the potential Bottleneck problem.
The Bottleneck problem is reflected in existing congestion
patterns on the Santa Ana Freeway (I-5) between Culver
Drive, and SR 55 and beyond. The Bottleneck problem
exists today due to the convergence of the Garden Grove
(SR 22), Costa Mesa (SR 55) and Orange (SR 57) Freeways in
this area, funneling very heavy traffic volumes through
the I-5 corridor. The problem will intensify in the
future due to the construction of the ETC and FTC and a
lack of existing and planned high-capacity transportation
I-1
facilities parallel to I-5 that can accommodate projected
traffic demand.
THE STUDY AREA
The Bottleneck study area is bounded by the Riverside
Freeway (SR 91) on the north, the proposed ETC on the
east, Moulton Parkway on the south, and SR 55 to the west
(see Figure 1).
Figure 1 - Bottleneck Study Area
Los Angeles
Befnafdino Co.
Riverside Co.
a.. co,,~o.
' ' ' ~ = ~oo~w Lk
o , , 3 · , . ,.,,.~ ' ' ' ';':" ' ' '''<~':''
The study area includes portions of the cities of Tustin,
Irvine, Orange, Santa Ana, Villa Park, and Anaheim and the
I-2
North Tustin area of the County of Orange. The area is
diverse, containing a variety of development and landforms
which contribute to its setting and character. The
westerly portions in the City of Orange and in North
Tustin are generally developed. In this area, flat
topography facilitated extensive development of medium-
priced single-family residences, as well as apartments and
commercial facilities. The Hispanic community of E1
Modena is located within this area along Chapman Avenue
west of the foothills. To the east, the area transitions
through rolling foothills to the steep-sided Santa Ana
Mountains. This area is occupied by hillside residential
communities, including Orange Park Acres, Cowan Heights,
Lemon Heights, Panorama Heights, and Barrett Hill. Homes
in these larger-lot hillside areas are more expensive.
There are several scattered undeveloped areas, but
generally this portion of the study area is also
developed.
The northeastern' portion of the Study area has diverse
terrain, supporting lush vegetation and woodlands in a
network of canyons and ridgelines and along Santiago
Creek, which is a major tributary to the Santa Aha River.
Much of this area is presently open space or parkland.
Irvine Park, Santiago Oaks Regional Park, and the proposed
Peters Canyon Regional Park are located in this area, as
are Holy Sepulchre Cemetery and a new campus of Santiago
'Community College. To the southeast, the study area is
presently rural in character, with extensive agricultural
fields and orange groves. Within this area, the Irvine
Ranch maintains its agricultural headquarters at Irvine
Boulevard and Myford Road.
I-3
In addition to the existing land uses, major portions of
the Bottleneck area are planned for 'future development.
Among the areas which are proposed for development are the
East Tustin Specific Plan area, Upper Peters Canyon
Specific Plan area, and portions of the 18,000-acre area
in the City of Orange sphere of influence. This growth
will occur in the context of extensive development
anticipated in portions of the county adjacent to the
Bottleneck area.
NEED FOR ACTION
Projected growth will result in a continued worsening, of
traffic congestion in the Bottleneck area and elsewhere.
in Orange County unless major improvements are made.
With no Bottleneck connector and no new major
transportation improvements beyond those shown in Figure 2
for the Orange County Master Plan of Arterial Highways
(MPAH), the transportation system would be severely
overloaded. Traffic 'forecasts prepared by the Orange
County Environmental Management Agency (OCEMA) indicate
that traffic on I-5 will exceed 250,000 trips per day at
General Plan build-out. This represents a potential 23
percent traffic overload even after the planned widening
of the Santa Ana Freeway, construction of the ETC and FTC,
and upgrading of other existing freeways. Arterial
streets paralleling I-5 will also be severely congested.
Improvements to the circulation network will be essential
if mobility and accessibility to and within the urbanized
core of Orange County is to be maintained.
EXISTING AND PROPOSED ARTERIAL SYSTEM
The arterial street system in the Bottleneck study area
I-4
Foothiil/Eastem/i-5
Bottleneck Analysis
FIGURE 2
MASTER PLAN OF
ARTERIAL HIGHWAYS
Existing Freeways
Proposed Transportation
Corridors
GRUEN ASSOCIATES
contains discontinuities which contribute to congestion on
I-5. The discontinuity is particuiarly evident in the
developing areas of Irvine, East Tustin, East Orange,
Anaheim Hills and east of Lemon Heights, where many
planned major streets are not yet constructed or are not
built to full MPAH standards. In addition, the number of
major MPAH east-west streets is limited; only Santiago
Canyon Road, Portola Parkway (proposed), Irvine Boulevard
and Bryan Avenue are planned as continuous major routes,
but none of these are fully improved today. As a result
of existing and projected system discontinuities, the few
continuous east-west routes through the Bottleneck area
including I-5 are projected to carry very heavy traffic
volumes.
OBJECTIVES OF THE STUDY
The Foothi!l/Eastern/I-5 Bottleneck Analysis is a
feasibility study rather than a specific route location or
design study. As such, the study is intended to address
broad feasibility issues rather than specific alignment or
design issues. If Bottleneck solution concepts are
adopted as a result of this study, detailed alignment or
design studies of the selected alternatives may be
initiated by the appropriate agencies.
The Bottleneck analysis
objectives:
had the
following study
Identify the magnitude and timing of the Bottleneck
problem.
Define and evaluate a range of alternatives to
address the Bottleneck problem, balancing
transportation objectives with community and
environmental concerns.
I-5
Determine whether a connector from the regional
freeway system and SR 22 to the proposed FTC and ETC
would be feasible.
II. DEFINITION OF BOTTLENECK ALTERNATIVES
Based on the analysis of existing and projected
transportation needs, three basic categories of Bottleneck
improvement alternatives were defined in addition to the
Baseline Alternative: Freeway Connectors, Arterial
Improvements-, and Regional Freeway System Alternatives.
Within these four categories, the following alternatives
were identified for analysis (see Figure 3 on following
page).
I-6
KRD
2C,
TUSTIN
3D
Foothill/Eastern /I-5
Bottleneck Analysis
FIGURE 3
1 MPAH BASELINE
(NO PROJECT)
2 FREEWAY
CONNECTOR
ARTERIAL
IMPROVEMENT
4 REGIONAL
FREEWAY SYSTEM
IIIlll
ALTERNATIVES c.uE. ^ssoc,ATEs
(2)
MPAH Baseline Alternative (No Project)
Freeway Connector Alternatives
2A - Santiago Creek
2B - Chapman Avenue
2C - Foothill Depressed
2D - Foothill Partial Tunnel
2E - La Colina Drive
(3) Arterial Improvement Alternatives
3A - Santiago Canyon Road
3B - Chapman Avenue
3C - 17th Street/La Colina Drive
3D - Irvine Boulevard
3E - Walnut Avenue
3F - Moulton Parkway
(4) Regional Freeway System Alternatives
4A - I-5 Elevated Guideway Extension & SR 55 widening
4B - SR 57 Extension to 1-405 and SR 73
MPAH BASELINE ALTERNATIVE {CATEGORY
This alternative provides the baseline condition against
which the other alternatives are measured. This
alternative assumes that the MPAH will be in place at the
time of General Plan build-out and that no additional
arterial or freeway improvements will be provided beyond
the MPAH level, except for the planned widening of I-5 and
other existing freeways in the county. Impacts associated
with bringing existing major streets up to MPAH standards
and constructing new MPAH facilities including the ETC~ and
FTC will be addressed during the development of these
facilities. As they are not part of the Bottleneck
analysis, potential impacts from those MPAH projects are
not addressed in this report. -
I-7
FREEWAY CONNECTOR ALTERNATIVES (CATEGORY 2)
These alternatives have been' developed as freeway
connectors linking SR 55 and SR 22 to the west with the
ETC and FTC to the east. Alternatives 2A and 2B represent
indirect connections from SR 55 and SR 22 to the FTC via
the ETC, while Alternatives 2C, 2D and 2E represent direct
freeway links between SR 55/SR 22 and the ETC and FTC.
Each of these alternatives has been sized to meet
projected future traffic demand and includes interchange
connections to major arterials.
Alternative 2A - Santiago Creek Freeway Connector
This alternative would extend from the Garden Grove
Freeway (SR 22) northeast along the Santiago Creek
Channel, east and south along Santiago Canyon Road
(generally north and east of the road), across the
proposed Peters Canyon/Weir Canyon Road to the proposed
ETC. The Santiago Creek Connector would require four
travel lanes to accommodate projected travel demand. A
300-foot right-of-way (ROW) would be provided for a
combination of at-grade and depressed (20 feet below
grade) freeway through thi~ area. ~The ROW would be
widened to 370 feet for approximately 1,500 feet beginning
1/4 mile west of Newport Avenue to accommodate side slopes
through this cut area.
Alternative 2B - Chapman Avenue Freeway Connector
The Chapman Avenue Alternative (2B) also begins at the
Garden Grove Freeway and extends east along the south side
of Chapman Avenue, then over the hill east of Crawford
I-8
Canyon Drive. The
Peters Canyon/Weir
the ETC. The Chapman Avenue
travel lanes to acco~,~odate
lanes would be accommodated
depressed (20 feet below
alignment would cross the proposed
Canyon Road and c6ntinue southeast to
connector would require six
projected demand. These six
within a 300-foot ROW for a
grade) freeway, widening to a
420-foot ROW through the hilly terrain east of Crawford
Canyon Road to accommodate the required side slopes.
Alternative 2C/2D - Foothill Depressed/Partial Tunnel
Connector
The route.of these two freeway connector alternatives is
the same; they differ in that Alternative 2C remains
depressed in open cut throughout its length, while
Alternative 2D assumes deep bored tunnel construction for
a 1.04-mile sep~ent of the route through the hills east of
Newport Avenue in an attempt to minimize residential
impacts. Both alternatives would begin at the Garden
Grove Freeway and extend east along the approximate
alignment of Larkstone Drive. East of Hewes Avenue, the
route would curve southeast toward Newport Avenue, then
parallel Foothill Boulevard along the approximate location
of La Limonar Road. These two alternatives then extend
east through Lemon Heights and interchange with the ETC
and the FTC.
Both alternatives would be eight lane facilities. A 300-
foot ROW is assumed for the at-grade, depressed and
embankment sections through the flatter areas. Through
the hills the ROW would vary, with widths ranging from 300
feet to 640 feet.. Roadway cuts up to approximately 120
feet deep and over 600 feet wide would be required to
cross the hills. The proposed ROW for Alternative 2D, the
I-9
partial tunnel, would
the tunnel section.
widen to 420 feet'to incorporate
Alternative 2E - La Colina Drive Freeway Connector
The La Colina connector would also begin at the Garden
Grove Freeway but immediately turns southeast toward
Newport Avenue. The route would cross 17th Street and
continue southeast along the approximate alignment of
La Colina Drive until near Browning Avenue where the route
would curve northeast to the ETC and FTC. Projected
travel demand requires an eight-lane freeway facility.
These eight lanes would be accommodated within a 300-foot
ROW for the lengthof the primarily depressed (20 feet
below grade) freeway.
ARTERIAL IMPROVEMENT ALTERNATIVES (CATEGORY 3)
These alternatives were developed for analysis of possible
improvements to important east/west MPAH arterials which
have potential to provide additional traffic capacity and
Bottleneck relief. Six alternatives were chosen based on
their M. PAR classification of secondary arterial or higher
and good connections to the regional transportation
system.
Alternative 3A - Santiago Canyon Road
This arterial would have the capacity to accommodate
projected build-out traffic demand; therefore no widening
beyond the MPAH level is required, and no arterial
improvement has been defined for this alternative.
1-10
Alterna%ive 3B - Chapman Avenue
Chapman Avenue would also accommodate projected future
traffic demand except for one segment west of Yorba
Street, and no further widening beyond the MPAH level is
necessary for most of the length of this route.
Therefore, no arterial improvement has been defined for
this alternative.
Alternative 3C - 17th Street/La Colina Drive
As shown in the MPAH, 17th Street is designated as a Major
Arterial from the SR 55 Freeway to Newport Avenue, with a
capacity of 50,006 to 54,000 ADT at LOS D and E,
respectively. La Colina Drive extends from Newport Avenue
to Browning Avenue as a MPAH Secondary Arterial with a
capacity of 22,000 to 24,000 ADT at LOS D and E,
respectively. To accommodate additional arterial traffic
through this area, the following possible MPAH
modifications were 'evaluated for Alternative 3C: 1) La
Colina Drive extended west to 17th Street and east to the
ETC; and 2) the entire length of La Colina Drive (existing
and proposed extensions) widened to Major Arterial width
(120 foot row) to match the MPAH classification of 17th
Street.
Alternative 3D - Irvine Boulevard
Irvine Boulevard is classified on the MPAH as a 120-foot
Major Arterial from SR 55 to Newport Avenue and from
Browning Avenue eastward. Between Newport and Browning,
the route is classified as a 100-foot Primary Arterial.
Since projected future traffic demand exceeds the MPAH
capacity, further improvements were evaluated for this
arterial:
1-11
SR 55 - Newport Avenue
: No Change from MPAH
Newport Avenue - Red Hill Avenue : Develop special 6-lane
cross-section within
100-foot MPAH Primary
ROW
Red Hill Avenue - Browning Avenue: Upgrade
Browning Avenue --~=~
100-foot MPAH
Primary to 120-foot
Major classification.
: Consider use of special
8-lane cross section
within 120-foot MPA/{
Major ROW
Alternative 3E - Walnut Avenu~
Projected future traffic demand can be accommodated within
the MPAH designations for Walnut Avenue. Therefore, no
widening beyond MPAH levels would be needed, .and no
arterial improvement has been defined for this
alternative.
Alternative 3F - Moulton Parkway
Moulton Parkway is designated on the MPAH as a Major
Arterial with a capacity of 50,000 to 54,000 ADT at LOS D
and E, respectively. As a Major Arterial, this roadway
could accommodate the projected traffic demand west of the
proposed Myford extension. At the intersection of Moulton
and Myford, however, an at-grade intersection would be
overloaded given the very high projected demand at this
location. Therefore, a future grade-separated interchange
is proposed at this location.
1-12
REGIONAL FREEWAY SYSTEM ALTERNATIVES (CATEGORY 4)
Two regional system alternatives-have been identified for
evaluation: Alternative 4A represents a possible upgrade
of I-5 and SR 55 through the Bottleneck area to provide
additional capacity; and Alternative 4B reflects the
possible future extension of SR 57 south to 1-405 and SR
73 as an important regional freeway system component which
might help to relieve I-5 congestion and enhance regional
transportation system performance. However, because
Alternative 4B is located outside of the Bottleneck area
and is not defined as a Bottleneck alternative within the
scope of this analysis, it is addressed only in
preliminary te~ms in this study. If appropriate,
subsequent regional studies of the extension of SR 57 may
be initiated by the responsible agencies.
Alternative. 4A - I-5 Elevated Guideway Extension and SR 55
Widening
The planned improvement of I-5 will provide a widened
e~ght lane facility plus auxiliary lanes and high
o~cupancy vehicle (HOV) lanes. However, even these
improvements will not accommodate projected future General
Plan build-out traffic demand for this portion of I-5. In
response to the projected demand, if the elevated guideway
proposed by OCTD for the Santa Aha Corridor were extended
through this segment of I-5 and if the available median
HOV space were then converted to mixed-flow traffic lanes,
I-5 would have the potential to accommodate build-out
traffic demand in this corridor. In addition, SR 55 would
be widened from 6 mixed-flow lanes to 8 mixed-flow lanes
between I-5 and SR 22 under this alternative to
accommodate projected demand.
1-13
Alternative 4B - SR 57 Extension to 1-405
The SR 57 (Orange) Freeway presently terminates at I-5
near SR 22. The southern extension of the SR 57 Freeway
is shown on the M~AH as a proposed state freeway.
Although beyond the scope of the Bottleneck study, the
possible extension of SR 57 to 1-405 has been given
initial consideration as a Potential solution to
congestion along I-5. The SR 57 extension would be an
eight-lane facility from I-5 south to 1-405 with a
capacity of 145,000 to 161,000 ADT at LOS D and E,
respectively. Additional capacity would also be required
to the east along 1-405 to provide for the connection to
SR 73.
III EVALUATION OF ALTERNATIVES
A summary evaluation of the Bottleneck alternatives is
presented in Table 1 and in the following pages. The
following evaluation factors are included:
·
·
·
·
·
Transportation System Performance
Socioeconomic Effects
Land Use Compatibility
Key Environmental Effects
Cost and Financial Feasibility
As shown in Table 1, evaluation for Alternatives 1, 3A,
3B, and 3E were not included; no additional improvements
beyond MPAH levels were found to be needed for these
alternatives. These alternatives and all Bottleneck
alternatives will have various impacts associated with
implementing MPAH improvements. However, these MPA/{
improvements are assumed to be in place in this study and
1-14
therefore potential impacts from these MPAH projects are
not analyzed in this report.
TRANSPORTATION EVALUATION
Projected Traffic Volumes and Capacities - Future traffic
volumes and capacities on the planned regional freeway
system were evaluated, assuming General Plan build-out
(post 2010), full development of the County MPAH, widening
of existing freeways (I-5, 1-405, SR 22, SR 55, SR 57, and
SR 91), and implementation of the Foothill, Eastern and
San Joaquin Hills Transportation Corridors. Volumes on
substantial portions of I-5, 1-405, SR 22, SR 55, SR 57,
and SR 91 are projected to exceed capacity. In the
Bottleneck area, future traffic is expected to exceed
capacity by up to 23 percent along I-5 and up to 18
percent along SR 55.
Alternative 2A would carry an estimated 44,000 vehicles
per day. It would increase volumes on SR 22, SR 57, the
FTC and part of the ETC. It would divert approximately
27;000 vehicles per day from I-5, and leave projected
traffic overloads in the I-5 corridor.
Alternative 2B would carry up to 86,000 vehicles per day
and would divert approximately 37,000 vehicles per day
from I-5 through the Bottleneck area; congestion would
remain in the I-5 corridor. Alternative 2B would increase
SR 22 volumes by 48,000 vehicles daily, contributing to
potential traffic overloads of up to 28. percent on this
route, even if SR 22 is widened to 8 lanes as assumed.
Alternatives 2C, 2D, and 2E are expected to carry
approximately 147,000 vehicles per day each. These direct
1-18
freeway connectors would be effective in reducing I-5
traffic by 64,000 vehicles and eliminating the I-5
congestion bottleneck. However,. these alternatives would
increase traffic volumes on the FTC and SR 22 by 44,000 to
57,000 vehicles per day, thus contributing to additional
overload and capacity problems, especially along SR 22 (up
to 34% over the capacity of an 8-lane SR 22 facility).
Alternative 3C has the potential to carry substantially
more traffic east of Holt Avenue if 17th Street were
extended to La Colina and La Colina Drive upgraded and
extended east. However, west of Holt Avenue, 17th Street
now carries 28,000 to 38,000 ADT and has limited capacity
to accommodate more traffic. It is estimated that 17th
Street volumes might be increased by 10,000 to 20,000
vehicles, while a La Colina extension and expansion would
carry approximately 25,000 additional vehicles. However,
this alternative would not by itself be able to
significantly relieve the I-5 bottleneck overload, due to
the limited potential for expansion of 17th Street.
Irvine Boulevard has excellent arterial system continuity
and therefore attracts high future volumes. The widening
and improvement of Irvine Boulevard as contemplated under
Alternative 3D would provide the capacity to accommodate
approximately 65,000 to 72,000 vehicles per day in a
corridor which will experience very high levels of future
demand (especially between Red Hill and Peters Canyon).
Moulton Parkwa~ is projected to carry up to 46,000
vehicles/day at build-cut and would be severely overloaded
at its intersection with Myford Road/Jamboree Road, thus
contributing to the Bottleneck problem. Under Alternative
3F, a grade-separated flyover interchange would be
1-19
provided at this location to accommodate the projected
demand on both of these key arterial routes.
Alternative 4A would widen SR 55 and utilize the I-5
median area to obtain additional general purpose traffic
lanes. Based on the MPAH build-out traffic projections,
demand on I-5 will exceed 250,000 ' vehicles daily. Even
with the planned I-5 widening to 8 lanes plus auxiliary
lanes plus HOV lanes, I-5 would not be able to accommodate
the projected demand. However, based on the proposed
conversion of HOV median space to mixed-flow traffic lanes
once an elevated transitway is provided, and the widening
of SR 55, Alternative 4A has the potential to accommodate
build-odt traffic demand in'this corridor.
Alternative 4B would carry up to 148,000 vehicles/day on
an extension of SR 57 south to 1-405. This alternative is
projected to reduce I-5 traffic by 22,000 to 41,000
vehicles/day between ETC and SR 57. It could
substantially reduce SR 55 traffic between 1-405 and SR 22
and increase freeway traffic in certain areas, while
reducing volume in other areas. The SR 57 extension would
have major regional traffic effects far beyond the defined
Bottleneck area, and should be evaluated in that broad
regional context, as well as for its local community
implications.
Traffic Origin-Destination Patterns
This study analyzed the projected future origins and
destinations of Bottleneck connector traffic, as well as
traffic on SR 22 and the Foothill Transportation Corridor
adjacent to the Bottleneck study area. Approximately 14%
1-20
of the traffic on the Bottleneck connector consists of
local trips with origins or destinations in the Bottleneck
area. The corresponding proportion of local traffic using
SR 22 and FTC in the vicinity of the Bottleneck area is
16% and 8%, respectively. Most of the traffic on or
approaching a direct Bottleneck connector would be through
traffic.
SOCIOECONOMIC EVALUATION
The introduction of a freeway into the Bottleneck study
area would affect both residential and commercial land
uses. Neighborhood character would be altered.
Established and planned communities would be divided by
the highway and school attendance boundaries and other
neighborhood patterns would be disrupted. In addition,
commercial facilities may develop around freeway
interchange locations and intrude upon the secluded
residential character presently found in many parts of the
area. The character of the existing and planned
neighborhoods would also be altered by increased noise,
reduction in air quality, and changes in the aesthetic
character of the area.
In addition to changes in neighborhood character,
construction of the freeway alternatives and some of the
arterial improvements would require extensive
displacement. Of the freeway alternatives,- Alternative
2B would displace the most residences (659) and businesses
(201). Alternative 2E would displace 561 existing homes
and eight businesses, while Alternative 2C and 2D would
require removal of 490 and 436 residences, respectively
and 12 businesses each. Alternative 2A would displace
1-21
a total of 217 homes and ten commercial structures. Of
the arterial improvement alternatives, only two would
require displacements beyond that required to implement
the MPAH: Alternative 3C would displace 56 homes and
three businesses; Alternative 3D would take ten
residences. No displacements would be required for
Alternative 4A unless additional right-of-way is required
along I-5. Major displacements may be needed to construct
Alternative 4B, depending upon the specific location and
design adopted for this major regional route.
Land Use Compatibility Evaluation
The alternatives traverse existing and proposed urbanized
areas, with the following generalized land use impacts for
the freeway alternatives:
Incompatibility with existing and planned residential
land uses - All of the alternatives introduce a high-
volume transportation facility into residential areas
with local neighborhood streets and low traffic
volumes, thus creating pressures for commercial
development, with potential effects on noise levels,
air quality, and aesthetics.
Relationship to open space and recreation areas-
Introduction of a freeway adjacent to open space and
recreation areas, such as Yorba Park, E1 Modena Park,
Saddleback Park, and the proposed Peters Canyon
Regional Park, may change the character of these land
uses. Although some existing recreation areas are
presently adjacent to a freeway (e.g., Yorba Park),
the majority of parks in the Bottleneck study area do
not adjoin major arterials and highways. Alternatives
2A, 2B, and 2C/2D propose introduction of a highway
next to Yorba Park at the corner of Chapman Avenue
and Yorba Street, the proposed Peters Canyon Regional
Park at Santiago Canyon Road and Chapman, and E1
Modena Park at Fowler _Avenue at Hewes Street, thus
potentially altering or diminishing recreational
opportunities and aesthetic experiences.
1-22
Relationship to co~u.ercial facilities - Construction
of a freeway adjacent to commercial activities may be
compatible with these facilities, such as along
Chapman Avenue (Alternative 2B). In these cases,
access to retail shops and offices may be improved by
the freeway and consequently, patronage may increase.
However, construction of such a freeway may also
displace residences and thus potentially reduce
market areas for businesses.
ENVIRONMENTAL EVALUATION
Topography - Each of the freeway connector alternatives
would require road cuts and fills at various points along
the alignment. Larger cuts would be required in the area
east of Crawford Canyon Road due to the hilly terrain.
Construction of the freeway alternatives would thus modify
the existing terrain: Alternatives 2A and 2E would
require relatively minimal cuts; Alternatives 2B, 2C, and
2D would need larger, more extensive cuts and wider side
slopes areas. Cuts for Alternative 2C would be the most
extensive (up to approximately 120 feet). Limited grading
would be necessary for arterial improvements, but no major
change in topography is anticipated.
Hydrology - Each of the alternatives would cross a
floodplain, and Alternative 2A would potentially conflict
with the Santiago Creek channel. These hydrologic issues
do not represent significant constraints in terms of
freeway construction; appropriate flood control measures
and designs would need to be considered with additional
costs involved.
Geotechnical - Each of the alternatives has the potential
for being constrained by geotechnical factors, in
particular Alternatives 2A and 2D.
1-23
Geotechnical constraints can be-mitigated with special
design or ground modification procedures, at additional
cost, and are not anticipated.to eliminate any potential
alternative from implementation.
Biology - The biological constraints for both freeway and
arterial improvement alternatives include possible impacts
to sensitive plants and wildlife and significant habitat.
Of the five freeway connector alternatives, 2A and 4Bhave
a high potential for biological constraint due to the
routing of these alignments along creek channels. The
remaining freeway alternatives would have moderate degrees
of disruption to riparian habitats and sensitive species.
Archaeological/Cultural Resources - Of the freeway
alternatives, 2A has six archaeological sites within the
proposed right-of-way; 2B has six paleontological sites.
Five fossil and two archaeological sites exist within the
proposed alignment of 2C and 2D; and two paleontological
and several potential historical sites are present within
the right-of-way for Alternative 2E. Alternative 3C also.
has two paleontological sites and several potential
historical sites within the proposed alignment, while
Alternative 3D would pass adjacent to the agricultural
headquarters of the Irvine Ranch and other historic
structures. One historic landmark, the Swamp of the
Frogs, was identified for Alternative 3F.
Air Quality - Transportation system improvements generally
create significant regional air quality benefits by
allowing a given number of vehicle trips to be served more
efficiently. However, each of the alternatives would have
the potential for reducing local air quality by
introducing high-volume transportation
1-24
facilities into residential areas 'where none presently
exist. The potential for reducing local air quality
should not create unhealthful, levels of air pollutants
unless background concentrations approach the state and
federal ambient air quality standard levels.
Noise - Noise levels would potentially increase with each
of the alternatives. Federal, state, and county agencies
have standards which govern the levels of noise permitted
on arterials, freeways, and outside and inside residences.
None of these standards would be exceeded by the proposed
alternatives. However, potential noise impacts on
sensitive receptors, such as schools, churches, residences
and hospi%als, may pose a constraint to alternative
alignments.
Aesthetics - Each .of the alternatives would traverse
existing residential communities. The alternatives would
be highly visible from adjacent residential areas,
particularly to hill area residents which have panoramic
views of the study area. The presence of a new freeway
would represent an intrusion upon the existing visual
character of the community. In addition, Alternatives 2A,
2B, and 2C/2D would be ' adjacent to recreational areas
(Yorba Park, proposed Peters Canyon Regional Park, and E1
Modena Park). Introduction of a high-volume
transportation facility into or adjacent to these parks
would detract from the visual quality of the surrounding
area.
COSTS AND FINANCIAL FEASIBILITY EVALUATION
Table 2 summarizes the estimated construction
of-way cost estimates for the alternatives.
and right-
1-25
347
3O0
463
As the longest route, Alternative 2A would have the
greatest freeway corhgector construction cost (with the
exception of the partial tunnel Alternative 2D), but
relatively less right-of-way cost compared to the other
alternatives. Alternative 2B (Chapman Avenue connector)
has relatively high right-of-way and construction costs,
while Alternatives 2C and 2E are similarly priced at
approximately $300 million each. Alternative 2D, partial
tunnel through the hills, saves $27 million for right-of-
way but costs $190 million more for construction.
The 17th Street/La Colina Drive extension (Alternative 3C)
would cost an estimated $45 million with comparatively
high right-of-way costs. By comparison, Alternatives 3D
and 3F would cost $4 to $5 million each, and could achieve
equivalent capacity increases with significantly lower
right-of-way costs.
1-26
The 4A
existing freeway rights-of-way
construction cost of $143 million.
cost approximately $850 million
additional costs required for the
alternative along 1-405 to SR 73.
Alternative would be constructed generally within
at an estimated
Alternative 4B would
with significant
connection of this
Availability of Funds
The direct freeway connector alternatives would require
funding in the range of $300 to $463 million. Given the
substantial current shortfall in monies for transportation
improvements, the prospects are highly uncertain for
identifying new sources which could provide $300 to $463
million. In addition, an estimated $2 billion cost would
be required to implement the major freeway improvements
assumed in the baseline to this study1. Alternatives 3D
and 3F would each require new funding in the' $4 to $5
million range, an amount that may be feasible through
combinations of public and private sector sources.
Alternative 4A may potentially be funded with conventional
federal and state sources if appropriate priorities are
established for such a project, including support from
OCTD for the concept of an elevated quideway extension.
Alternative 4B would be classified as a regional
transportation system element, thereby qualifying for
traditional state-federal freeway monies. In addition,
joint funding opportunities and potential net savings may
be possible if major flood control improvements along the
Santa Ana River are coordinated with highway improvements.
1-27
1Escalated cost of improvements to existing freeways
and highways as reflected in Table 1 of the Orange County
Transportation Commission Fifteen-Year Transportation
Investment Plan, December 1983.
IV. SUMMARY OF PUBLIC INVOLVEMENT PROGRAM
An extensive program of public involvement was developed
to commtmicate Bottleneck Study findings to the citizens.
It included ~he Policy Committee, the Technical
Information Exchange Group, consultation with key groups,
the use of communication resources, and the conduct of
p,,blic info~,ation meetings.
Policy Committee
The Bottleneck Study Policy Committee consisted of city
council representatives from Anaheim, Irvine, Newport
Beach, Orange, Santa Ana, Tustin, Villa Park, and
representatives of the Orange County Board of Supervisors,
Caltrans, and SCAG. The Policy Committee's role was to
provide policy guidance to the study and to review study
team recommendations and proposals. The Policy Committee
held four meetings with the study team during the project,
and provided valuable input and policy direction to the
study. Major issues raised by the Policy Committee
included:
·
o
o
o
o
·
R~gional growth interests and needs
ETC alignment selection
Individual community policy issues
Criteria for evaluating alternatives
Cost and environmental analysis
Landowner and developer involvement
Alternative methods of financing,
feasibility and cost effectiveness
financial
1-28
Technical Information Exchange Group
The Bottleneck Study Technical Info~,,ation Exchange (TIE)
group consisted of representatives of the cities, the
county, state, -the development community, homeowner
groups, and other community organizations. The TIE group
reviewed study progress and exchanged information as
needed to insure that the study team had adequate
technical information. The TIE group held six meetings
with the study team during the course of the project
through the development and review of the draft reports,
and provided an effective means for communicating
comprehensive technical data during the project. Major
issues addressed by the TIE group included:
· Need to maintain the "No Build" alternative.
· Coordination with ETC route location analysis
· Technical information regarding traffic forecasts
· Review of Bottleneck alternatives, analysis and
evaluation
Involvement of Key Groups
Key organizations and groups were identified and their
input sought to help reflect major issues and concerns
during development of alternatives and evaluation of
impacts. Meetings were held with the following
organizations:
ORANGE COUNTY - EMA
CITY OF IRVINE
CITY OF SANTA ANA
CITY OF VILLA PARK
ORANGE PARK ACRES
NORTH TUSTIN MAC
ORANGE COUNTY SUPERVISORAL
DISTRICT OFFICES
CITY OF TUSTIN
CITY OF ORANGE
CITY OF YORBA LINDA
IRVINE COMPANY
CITY OF TUSTIN
FOOTHILL COMMUNITIES
ASSOCIATION
1-29
Bottleneck Study Communication Resources
The media provided an important means of communication to
keep the community informed during the Bottleneck study.
Notices in community calendar columns, press releases,
public service announcements and contacts with media
personnel were used to disseminate information.
· Letters, mail-outs, posters and fliers were used to inform
the community of Bottleneck meeting dates and times,
issues and general information. Notices were distributed
by the Orange County Transportation Commission by bulk
mail and hand-carried to community activity centers.
Initial mailing lists for the Bottleneck study were
developed from available resources and expanded throughout
the study with addresses of citizens who participated in
the study.
Information handouts were prepared to summarize the
highlights of individual meetings and to provide
discussion~ material for comment and review. Meeting
comment sheets were utilized for citizens to express
concerns and opinions on Bottleneck issues. The comment
sheets supplemented verbal comments received during the
public information meetings and open house workshops.
PUBLIC MEETINGS
Direct citizen participation in the Bottleneck Study was
achieved through a series of public meetings at project
milestones. Residents, property owners and business-
persons provided community viewpoints to supplement
technical aspects of the study. The following meetings
were held:
1-30
August 1, 1985 - INITIAL PUBLIC INFORMATION M~.~TING - The
initial meeting was conducted in two Parts: the first
included an infozmal workshop/open house with dialogue
between citizens and study team members; and the second
included fo£mal presentation of project elements with
public participation, questions and comments.
Approximately 125 persons attended the open house and the
formal meeting.
October 3, 1985 - SECOND PUBLIC INFORMATION MEETING - This
meeting was organized as an informal walk-in session with
dialogue between citizens and study team members,
providing review of preliminary alternatives illustrated
on wall maps. Comment sheets and handouts were provided
for the approximately 50 persons in attendance.
January 30, 1986 - THIRD PUBLIC INFORMATION MEETING - An
informal open. session between 5:00 and 7:00 p.m. provided
a one-on-one review of the preliminary evaluation of the
alternatives. At 7:00 p.m., the study team slide
presentation-highlighted the findings of the evaluation.
The meeting was then open to public discussion.
Approximately 250 persons attended the Open House. A
handout was distributed which summarized the findings of
the analysis and co~unent sheets were also provided.
At the request of the meeting participants, a straw vote
was taken to assess the general level of support for the
alternatives. The baseline alternative (no Bottleneck
improvement) was favored by the largest number of
attendees, followed by Alternatives 4B and 4A. Among the
arterial improvements, only Alternatives 3F and 3C had a
limited number of supporters.
1-31
The public identified a variety of community concerns and
thus helped to focus the Bottleneck technical analysis and
evaluation of alternatives. The'se included:
Identification of established residential communities
within the study area, whose residents moved .here
with no expectation of having a major regional
transportation facility through the community.
Belief that residents of the area do not want or need
new freeways or major arterials, and can continue to
use existing access routes.
Concern about equity issues; study area residents
would experience the adverse impacts while new
developments outside the study area would benefit
from a new freeway through the Bottleneck area.
Concern that Bottleneck alternatives cannot be
evaluated until the Eastern and Foothill Corridors
are defined and located.
Concern for cost per mile.
Need to .take into account impacts on major
development plans such as the proposed East Tustin
Plan.
Consider effects on property values and loss of
property and sales tax revenues.
Evaluate transportation needs from an overall basis
looking outside the Bottleneck study area.
Upgrade existing facilities rather than constructing
a new freeway through this developed residential
area. Alternative 4A would be better than a new
freeway connector.
v. FINDINGS AND CONCLUSIONS OF STUDY
Orange County is in a period of dynamic growth and change,
and as a result, future transportation plans and policies
are still in the formative stages. Because the Bottleneck
1-32
analysis is being conducted in this overall environment of
growth and change, the findings of ~the study must be
considered from multiple perspectives.
Political Issues - New approaches to interagency
cooperation including the Joint Powers Agency (JPA)
are being implemented to plan, design and build major
transportation facilities. The processes and
procedures for evaluation and decision-making by such
agencies which are currently being developed will
influence the consideration of Bottleneck
altneratives.
Funding Issues - There is a large gap between
identified countywide funding needs and available
monies. Various measures are under consideration to
help address the shortfall and meet existing and
future transportation needs, but no comprehensive
solutions are available at this time. Private sector
funding support and user fees are approaches
currently being explored.
'Technical and Transportation - The existing
transportation system and its major elements are
under review. Major new location options for the ETC
are being investigated, including a shift to the east
to connect the ETC with SR 133. Modifications to the
western portions of the FTC are also under
consideration. Various I-5 widening options are
under detailed study by Caltrans. The Orange County
Transit District transitway planning process is
underway. New high-occupancy vehicle lan9 concepts
are being tested and evaluated by Caltrans and the
Orange County Transportation Commission. At the same
time, major land use planning and development
proposals are being considered within the County
which could significantly affect the magnitude and
location of future transportation demand patterns.
RECOMMENDATIONS
Given the currently uncertain nature of transportation
planning and development in Orange County, no single
1-33
/
optimum course of action for the Bottleneck problem can be
identified. The most prudent approach would be to keep
major options open, maintain flexibility, and monitor the
rapidly evolving political, financial and technical issues
related to the Bottleneck problem. Specific
recommendations for OCTC actions include the following:
Coordinate with the JPA to develop procedures for
analysis, evaluation and decision-making for the FTC
and ETC in light of the findings documented in this
study.
Coordinate with OCEMA, local communities, and the
public regarding Phase. 2'route location studies for
the ETC as these studies and analyses may affect
the feasibility of various Bottleneck alternatives.
Continue investigation of the feasibility of
alternative funding sources and potential revenues
for a) countywide transportation needs, b) major new
transportation corridor development and c) possible
Bottleneck solutions. Financial feasibility is
critically important for Bottleneck alternatives,
where there exists no long-established system plan or
funding commitment for new transportation
improvements.
Initiate comprehensive planning to expand the
Bottleneck study area. A broadened definition of
the Bottleneck problem and possible solutions would
permit consideration of transportation system
alternatives from a regional standpoint and avoid
piecemeal modification of the MPAH.
Adopt coordinated land use and transportation
planning policies which can help to guide -the
development of major transportation facilities.
Questions of whether future growth should be focused
on current urban centers and urban core areas, or
dispersed to less developed areas of the county
and adjacent areas could be addressed in the
context of regional transportation needs. Quite
different transportation system plans might be needed
to serve alternative development scenarios under
these policies.
1-34
Alternatives Recommended for Further Consideration
In the immediate future, some transportation decisions
must be made as development proceeds. The following
discussion is intended to provide a basis for near-term
decision-making on Bottleneck alternatives under two
different assumptions:
ASSUMPTION 1 - If the current MPAH is re4:ained
without major change in FTC or 'ETC locations,
capacity and connections, and if demographic
assumptions remain consistent with the current
General Plan.
ASSUMPTION 2 - If the current MPAH is modified to
relocate the FTC or ETC from their presently proposed
locations.
Assumption 1 - If Current MPAH is Retained
This section recommends alternatives proposed for further
consideration by the Transportation Commission, the county
and the cities. The reco~mL,endations are based on the
technical analysis and evaluation documented in the
Bottleneck study, and assume that the current MPA/{
locations for the FTC and ETC will be retained.
The study proposes that the following Bottleneck
alternatives be given additional consideration:
1-MPAH Baseline
2C-Foothill, depressed
2D-Foothill, partial tunnel
2E-La Colina
3C-17th Street/La Colina
3D-Irvine Boulevard
3F-Moulton Parkway -
4A-I-5/SR 55 Improvements
4B-SR 57 Extension to 1-405 and SR 73
1-35
Alternatives 2A, 2B, 3A, 3B and 3E would not eliminate
Bottleneck congestion, but would ~reate potentially
significant community impacts.- Therefore, these five
alternatives are recommended for elimination from further
consideration un~er the Assumption 1 scenario.
The alternatives recommended for further evaluation each
have advantages and disadvantages associated with them.
Alternative 1, the MPAH Baseline, would fail to relieve
I-5 Bottleneck overloads projected at build-out, but would
avoid the major community impacts which would accompany
most of the other Bottleneck alternatives. Alternatives
2C, 2D, and 2E would carry approximately 147,000
vehicles/day, but with significant displacement and
community disruption. Of these alternatives, 2E would
displace the greatest number of residences: 561; 2C and 2D
would displace approximately 490 and 436 residences,
respectively. From a transportation standpoint,
Alternatives 2C, 2D and 2E would provide localized
congestion relief in the Bottleneck area. From a regional
perspective, however, these alternatives would shift the
congestion to the Garden Grove Freeway area.
The regional freeway upgrade alternatives, 4A and 4B,
would also provide substantial Bottleneck relief and
additional traffic capacity. Alternative 4A would not
require residential displacement if accomplished within
existing freeway rights-of-way; however, Alternative 4B
could result in major displacement even if located along
the Santa Ana River channel. The arterial improvement
alternatives proposed for additional consideration would
carry much less traffic than the freeway connector
alternatives, but the community impacts would also be much
less severe. For example, 3C, 3D, and 3F would
1-36
carry an additional 15,000 to 40,000 vehicles/day while
these alternatives would displace 56, 10 and 0 homes,
respectively.
Assumption 2 - If MPAH is Modified to Relocate ETC or FTC
Under this assumption, a modified regional transportation
system pattern might be developed which could shift
Foothill and Eastern Corridor traffic to the north, away
from the more intensely urbanized central Orange County
areas. If these modifications occur,, it may have
important implications for the Bottleneck alternatives
studied in this report:
Traffic networks and travel demand patterns would
change and traffic assignments would have to be
modified to reflect the changes.
The severity of the Bottleneck problem in the
southern part of the study area might be reduced if
the system modifications tend to shift traffic toward
the northern part of the Bottleneck study area.
Bottleneck problems in the northern part of the study
area (Santiago Canyon Road, Loma Extension) might be
increased if the system modifications tend to shift
traffic to the north.
In addition, development projections used in this study
for the northeastern portion of the Bottleneck area
assumed buildout of the current General Plan Land Use
Elements of the cities and the County, all of which are
subject to change.
Thus, no Bottleneck traffic conclusions can be drawn until
the possible modifications to the ETC and FTC are defined
and .system testing is completed and planning for the
northeastern portion of the study area undertaken. This
1-37
will be accomplished as part of the OCEMA Phase 2 studies
of the ETC and on-going planning effort~ by the cities and
County. In the interim, it would be premature to either
adopt or eliminate Bottleneck alternatives since their
effectiveness depends upon related system elements
i~cluding the ETC and FTC and adopted land use.
1-38
Prepared fi~r
(.)range Coun~ Transport~tcion Conamission
Executive Sun'tm~rv
I
T()I~[, R(),.\I) l?l.:..\.~ll~,l[',rl
[:oothill/l':a.stcrn
(:orridor.s
GRUEN ASSOCIATES
l~mpar~zd
Orange (:ountv Transportation (]ommission
l~rcparcd by
GRUEN A$$OCIATI=$
.Nlay, 1986
I. EXECUTIVE SUMMARY
This report documents the results of~ an initial toll road
financial feasibility study for the Foothill and Eastern
Transportation Corridors. ~iven the preliminary nature of the
investigations performed to date, it should be recognized that if
a decision is made to further pursue development of toll
facilities in these Corridors, detailed traffic, revenue, cost
and financing studies would be required to establish financial
feasibility.
Within this context, the following key findings and conclusions
have emerged from this study effort:
Ne
The most crucial aspect of toll road financial feasibility
is the opening year revenue projection, wherein at least 125
percent debt coverage ratio would be required if toll
revenues were the sole source of financing.
Partial financing of the Foothill and Eastern Corridors will
be accomplished through proceeds from the Major Thoroughfare
and Bridge Fee Program, estimated to total $341 million from
1985 through General Plan BUildout. Thus, initial bond size
could be reduced by use of fees collected prior to start of
construction, which would reduce annual debt service. In
addition, fees collected after construction could be applied
to any revenue shortfall.
The Orange County EMA traffic projections utilized for this
study are for General Plan Buildout (post year 2010).
Opening year (1995) traffic and toll revenue estimates were
made based on a comparison of buildout versus 1995
population estimates for the study area. Given the
importance of opening year traffic and revenue projections,
it is recommended that 1995 traffic projections be made if
toll financing is to be pursued further.
e
Based on available buildout traffic projections and
approximate opening year figures, toll revenue estimates
have been made using appropriate traffic diversion curves.
Such toll revenues have been combined with fee program
estimates to assess the overall financial feasibility
picture for the Foothill and Eastern Corridors. Key
findings are as follows:
A combined Foothill and Eastern toll facility would
cover an estimated 21 percent of debt service in the
opening year (1995) and would reach an estimated 34
percent at buildout (assumed to be 2015).
In the same timeframe, additional annual revenues
required from sources other than tolls and development
fees would be in the $26 million to $37 million per
year range.
Bo
The preceding findings are for a case without a freeway
connector from the Foothill Corridor to the Garden Grove
Freeway. If such a connector is built, it is estimated that
Foothill Corridor toll revenues would increase by 39
percent, while Eastern Corridor revenues would decrease by
roughly 10 percent. On an overall basis, toll revenues
would increase by 17 percent.
It is assumed that opening year for the Foothill/Eastern
toll facility would be 1995. Given the planned major
improvements of I-5 in this same timeframe, traffic and toll
revenues on the parallel Foothill toll facility could be
significantly reduced. No estimates of Such effects have
been made due to absence of a 1995 model run and definition
of I-5 improvements.
o
Based on the preceding findings,' an assessment of an
Eastern-only toll facility was conducted since such a
facility would face no direct competition and should be able
to capture a substantial share, of potential trips in this
Corridor. Conclusions of this analysis are as follows:
An Eastern-only toll facility would cover an estimated
'39 and 62 percent of debt service in the opening year
and buildout, respectively.
In the same timeframe, additional annual revenues
required from sources other than tolls and developer
fees would range from zero to $7 million.
These conclusions assume that one-half of the estimated
developer fe~s could be pledged to an Eastern-only toll
facility.
Table I presents a summary of the debt coverage ratios for
Foothill/Eastern and Eastern-only toll facilities, with and
without a freeway connector.
e
Based on information currently available and the results of
these preliminary financial feasibility results, it appears
that further in-depth consideration should be given to an
Eastern Transportation Corridor toll facility as opposed to
a combined Foothill/Eastern toll project.
TABLE 1
ESTIMATED TOLL FACILITY DEBT COVERAGE (PERCENT)
FOR OPENING YEAR AND GENERAL PLAN BUILDOUT
OPENING YEAR (1995)
GENERAL PLAN BUILDOUT
(2015)
FOOTHILL/EASTERN
WITHOUT WITH
CONNECTION CONNECTION
21% 25%
34% 40%
EASTERN
WITHOUT WITH
CONNECTION CONNECTION
39%' 35%
62% 56%