HomeMy WebLinkAboutNB 3 SIDEWALK REPAIR 05-20-85TO:
FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
DALE A. WICK, ASSISTANT CITY ENGINEER
AWARD OF BID FOR F.Y. '84-'85 SIDEWALK AND CURB REPAIR PROGRAM
(FILE #2298)
RECOMMENDATION:
It is recommended that the City Council, at their meeting of May 20, 1985, award
the contract for subject project to Arm and Hammer Concrete of Tustin, CA in the
amount of $32,760.43.
BACKGROUND:
This project encompasses repair of existing sidewalks which have been displaced by
tree roots at 104 locations throughout the city and repair of curb and gutter at
five locations.
Sealed bids for this work were opened on May 9, 1985 at 10:00 a.m. and were
received as follows:
Contractor Business Location Bid
Arm & Hammer Concrete
Dearmond Construction
Hardy & Harper Inc.
Walsh Engineering Co.
Damon Construction Co.
Harper Construction Co.
Tustln, CA
Alta Loma, CA
Santa Ana, CA
Anaheim, CA
South Gate, CA
Running Springs, CA
$32,760.43
34,792.60
35,936.41
38,343.21
40,156.60
50,002.42
The low bid is 8% below the.engineers estimate of $35,533.84. There is presently
$36,700.00 allocated in the F.Y. '84-'85 budget for this work.
Attached, for the City Council's information, is a tabulation of all bids
received.
Dale A. Wick
Assistant City Engineer
DAW:jr
Attachment
CC:
City Clerk
Finance Director
Street Maintenance Superintendent
0