DATE: OCTOBER 1, 198S Inter-Corn
TO:
FROM:
S U BJ ECT:
WILLIAM HUSTON, CITY MANAGER
DALE A. WICK, ASSISTANT CITY ENGINEER
AWARD OF CONTRACT FOR MAIN STREET WATER MAIN REPLACEMENT IMPROVEMENTS
RECOMMENDATION:
It is recommended that the City Council, at their meeting of October 10, 1985,
award the contract for subject project to Schuler Engineering Corporation of
Anaheim, CA, in the amount of $153,003.00.
BACKGROUND:
Subject project encompasses installation of a 10" diameter asbestos cement water
main along the northerly side of Main Street from "C" Street to Pasadena Avenue.
This installation will allow future retirement of an old 6" steel main which
exists between "C" Street and "A" Street and is designed to improve service
pressures as well as fire flows on Main Street.
Sealed bids for this project were opened at 10:00 a.m. on September 25, 1985 and
were received as follows:
Contractor Business Location Bid
Schuler Engineering Corp.
Macco Constructors, Inc.
Anaheim, CA
Paramount, CA
$153,003.00
$165,645.40
The low bid of Schuler Engineering Corp. is $28,783.25 or 23.17% over the
Engineer's estimate of $124,219.75. There is presently $171,400.00 allocated in
the budget for this work.
Attached, for the City Council's information, is a tabulation of all bids
received.
Dale A. Wick
Assistant City Engineer
DAW:jr
Attachment