HomeMy WebLinkAboutNB 4 STORM DRAIN IMP'S 11-19-84 · ' ~ NEW BUSINESS <::~ _ NO. FRON: $ U~,J EI;T: WILLIAM HUSTON, CITY MANAGER DALE A. WICK, ASSISTANT ¢I1"~ ENGINEER AWARD OF CONTRACT FOR "B" STREET HCDA STREET AND STORM DRAIN IMPROVEMENTS RECOMMENDATION: It is recommended thatthe City Council, at their meeting of November 19, 1984, award the contract for subject project to the low bidder, Griffith Company of Santa Aha, CA, in the amount of $94,700.67. BACKGROUND: Subject project encompasses realignment and construction of street improvements on 'B" Street fro~LMcFadden to 350' + northerly and construction of a storm drain on "B" Street from Mitchell Avenue t~Nisson Road.. Bids for this work were opened on .November 16, 1984 at 10:00 A.M. andWere received as follows: Business Contractor Location Bid Griffith Company Santa Ana, CA $ 94,700.67 Walsh Engineering Co. Anaheim, CA 99,338.45 Sully-Miller Co. Orange, CA 104,863.00 R. J. Noble Co. Orange, CA 106,400.45 The l~w bid i's 8.5% over the Engineer's estimate of $87,300.00.' There is presently $258,000.00 in HCDA funding available for improvements in this area. The County HCDA office has approved awarding of the contract to the low bidder. Attached for the City Council's information is a tabulation of all bids received. Dale A. Wick Assistant City Engineer DAW:Jr 'cc: City Clerk Finance Director . · ~,e: .OVEMB[R ~4, ~984 ~ lnter-Com TO: FROM: SUBJECT: WILLIAM HUSTON, CITY MANAGER BOB LEDENDECKER, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER AWARD OF BID FOR "B" STREET IMPROVEMENTS Due to the accelerated bid process and short time schedule for this project, "B" Street improvements (Phase I) northerly of McFadden Avenuey the bid opening for this project is not scheduled until Thursday, November 15, 1984. Consequently, the staff report and bid tabulations will be distributed on Monday, November 19th at the City Council meeting. 'Bob Ledendecker Director of Public Works/City Engineer BL:jr