HomeMy WebLinkAboutRPT 2 C.T. WELL PROJ. 10-15-84DATE: OCTOBER 9, 1984
REPORTS '
NO. 2
.10-15-84
Inter-Corn
FRON:
WILLIAM H~STON, CITY MANAGER
BOB LEDENDECKER~ DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
COLUMBUS-TUSTIN WELL PROJECT STATUS REPORT (FILE #2930A)
This report should be the final progress report for the Phase I portion of the
Columbus-Tustin Well Project. This phase is nearing completion with only two work
items remaining at the time of this writing. The following schedule has been
provided by the contractor, Stang Hy~ronics:
October 9 and 10 - Step drawdown test consisting of 8-10 hours of actual
pumping.
October 11 and 12 - Constant rate test consisting of 48 .hours of pumping at
maximum load.
At this point t~ese dates are only tentative an~ are still subject to change.
Boyle Engineering, the City's consultant, has indicated that the plans and.
specifications for Phase II of the project will be completed for bid advertisement
on November 5,. 1984 if the constant rate test is completed October 12th, a~
previously indicated, and if all results are favorable.
Bob Ledendecker
Director of Public Works/City Engineer
BL:jr