HomeMy WebLinkAboutRPT 5 C.T. WELL PROJ. 09-17-84'REPORTS NO. 5 TO: FROM: $ USJ ECT: WILLIAM HUSTON, CITY MANAGER BOB LEDENDECKER, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER COLUMBUS-TUSTIN WELL PROJECT STATUS REPORT As requested by Councilman Edgar, the following is a continuing status report on' the subject project: May 14, 1984 - Redevelopment Agency awarded contract for subject project to low bidder, Stang Hydronics, Inc. May 17, 1984 - Contracts mailed to Stang Hydronics in Rancho Cordova for their execution. June 12, 1984 - June 25, 1984 - Stang Hydronics confirmed contracts-in route to City by mail. Contracts have not been received by the City - Contractor assured Mr. Rowenhorst they were mailed June 22, 1984. Upon receipt of the contracts, they will be disbursed to appropriate parties for execution of contract. Start date is dependent upon contract execution date. July 10, 1984 - Pre-construction meeting held with Stang Hydronics. July 12, 1984 - Expected start date for security fence installation. July 18, 1984 - July 28, 1984 - Start date for test hole. Test hole completed. Drilling of test hole stopped at depth of 1,470 feet in lieu of 1,600 feet due to geological condition of test hole. July 31, 1984 - Commence testing as follows: a. Drift indicator survey b'. Geophysical logging and caliper survey c. Isolated aqoifer water quality sampling August 13, 1984 - Start date for reaming final well hole. August 20, 1984 - Completed reaming of final well hole in late p.m. to depth of 1,250 feet. - Completed caliper survey of final well hole. COLUMBUS-TUSTIN WELL PROJECT STATUS REPORT SEPTEMBER 17, 1984 PAGE 2 August 21, 1984 August 22, 1984 August 25, 1984 September 2-3, 1984 - September 13, 1984 - * September 17-18, 1984 - Expected start date of the placement of final well casing and screening. Estimated time of this placement is 24-30 hours. Completed placement of well casing and screen on August 22, 1984. Expected start date of gravel pack placement and grout seals. Estimated time of this phase is two days. Completed gravel pack placement and 'grout seals on August 23, 1984. Commenced well development phase (cleaning/surging). Expecte completion date of September 1, 1984. Commenced removal of excess dirt, pipe, equipment, etc. Removal of drilling rig from site. Expected start date for test pumping operation (56 continuous hours). Sound barriers will be rearranged closer to test pump motor to help reduce sound of operation. Equipment is coming from northern California. Delay caused by problems at previous job. The contract time limit is 120 calendar days with the start date of July 16, 1984 and a completion date of November 12, 1984. The contractor is well within the time frame allowed for this contract. Bob Ledendeoker Director of Public Works/City Engineer BL:jr