HomeMy WebLinkAboutRPT 3 CITY PKG STRUC. 09-04-84 y~ REPORTS NO. 3 DATE' September 4, 1984 FROH: SUBJECT: HONORABLE MAYOR AND CITY COUNCIL CO)~4UNITY DEYELOPMENT DEPARTi~ENT STATUS REPORT CONCERNING CITY PARKING STRUCTURE BACKGROUND AND DISCUSSION: On July 24, 1984 the Gfeller Development Company was notified in writing abut City concerns regarding cracks in the subject parking qriveway ramp. A meeting on August 23, 1984, was held at the site to view the cracks which were noted in the City'.s correspondence. Those who attended included City staff {Senior Planner, Plan Checker, Plan Check Consultant); Gfeller project managers, project structural engineer, soils engineer, and contractor. It was agreed that the structural engineer should review the plans and calculations for the garage and prepare a report for the Gfeller Development Company which will provide procedures and actions necessary to correct the problems. The structural engineer stated the report should be ready within a week and a half. A second meeting with all the participants was then scheduled for September 7, 1984 to review the report and recommendations. RECOI~ENDATION: Receive and file. Senior Planner AW:do DATE: TO: FROH: .SUBJECT: WILLIAM HUSTON, CITY MANAGER BOB LEDENDECKER, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER COLUMBUS-TUSTIN WELL PROJECT STATUS REPORT As requested by Councilman Edgar, the following is a continuing status report on the subject project: May 14, 1984 . Redevelopment Agency awarded contract for subject project to low bidder, Stang Hydronics, Inc. May 17 1984 . Contracts mailed to Stang Hydronics in Rancho Cordova for their execution. June 12, 1984 - Stang 14ydronics confirmed contracts in route to City by mail. June 25 1984 _ Contracts have not been received by the City - Contractor ' assured Mr. Rowenhorst they were mailed June 22, 1984. Upon receipt of the contracts, they will be disbursed to appropriate parties for execution of contract. Start date is dependent upon contract execution date. July 10, 1984 . Pre-construction meeting held with Stang Hydronics. July' t2, 1984 _ Expected start date for security fence installation. July 18, 1984 - Start date for test hole. July 28, 1984 - Test hole completed. Drilling of test hole stopped at depth of 1,470 feet in lieu of 1,600 feet due to geological condition of test hole. July 31, 1984 . Commence testing as follows: a. Drift indicator survey b. Geophysical logging and caliper survey c. Isolated aquifer water quality sampling August 13, 1984 - Start date for reaming final well hole. August 20, 1984 - Completed reaming of final well hole in late p.m. to depth of 1,250 feet. . Completed caliper survey of final well hole. COLUMBUS-TUSTIN WELL PROJECT STATUS REPORT AUGUST 30, 1984 PAGE 2 August 21, 1984 August 22, 1984 August 25, 1984 - September 2-3, 1984 - September 4, 1984 - September 6-7, 1984 - Expected start date of the placement of final well casing and screening. Estimated time of this placement is 24-30 hours. Completed placement of well casing and screen on August 22, 1984. Expected start date of gravel pack placement and grout seals. Estimated time of this phase is two days. Completed gravel pack placement and grout seals on August 23, 1984. Commenced well development phase (cleaning/surging). Expected completion date of September 1, 1984. Expected start date for removal of excess dirt, pipe, equipment, etc. Expected date for removal of drilling rig. Expected start date for test pumping operation (56 continuous hours). Sound barriers will be rearranged closer to test pump motor to help reduce sound of operation. Bob Ledendecker Director of Public Works/City Engineer BL:jr