WILLIAM HUSTON, CITY MANAGER
DALE A. WICK, ASSISTANT CITY ENGINEER
AWARD OF CONTRACT FOR F.Y. '83-'84 SIDEWALK AND CURB REPAIR PROGRAM
RECOMMENDATION:
It is recommended that the City Council, at their meeting of July 16, 1984, award
the dontract for the F.Y. '83-'84 Sidewalk and Curb Repair Program to Harper
Construction Company in the amount of $52,002.78. It is further recommended that
Finance be authorized to transfer funds from Account 2915, Street and Alley
Repair, to this project account in order to cover the shortfall in funding for
this project.
BACKGROUND:
Subject project encompasses repair of concrete sidewalk, drive aprons and curb and
gutter at 156 locations throughout the City.
Bids for this Work were opened at 10:00 a.m. on July 10, 1984 and were received as
follows:
Contractor
Business Location
Harper Construction Company
Arm & Hammer Concrete Removal
Damon Construction Company
Gabi Construction Company, Inc.
Nobest Incorporated
Running Springs., CA
Tustin, CA
South Gate, CA
La Habra., CA
Westminster, CA
Bid
$52,002.78
53,635.94
65,505.35
71.,889.44
84.,041.15
The low bid is 4 1/2% below the Engineers estimate of $54,427.65. There is
presently $49,100.00 budgeted for this project. Depending on final costs for the
project approximately $5,,500.00 will have to be transferred to this project from
Account 2915.
Attached for the City Council's information is a tabulation of all bids received.
Assistant City Engineer
DAW:jr
Attachment
CC:
City Clerk
Finance Director
Hugh West