HomeMy WebLinkAboutRPT 2 WIDEN IRVINE 07-16-84AGENDA
DATE: JULY 9, 1984
REPORTS
NO. 2
7-16-84
Inter-Corn
$ UBJ ECT:
WILLIAM HUSTON, CITY MANAGER
BOB LEDENDECKER., DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
IRVINE BLVD. FROM RANCHWOOD RD. TO CULVER DR. AND FROM
JEFFREY RD. TO SAND CANYON AVE.
Staff has received the following information from the County of Orange
EnviEonmental Management Agency regarding the subject project:
Commence Bid Advertisement ............................ June 26., 1984
Bid Opening ........................................... July 30~ 1984
Commence Construction on or about ..................... August 18, 1984
Complete Construction'on or about ..................... August 4,, 1985
This project will widen and reconstruct Irvine Blvd. from two travel lanes to four
travel lanes., and during the term of construction it will be under the
jurisdiction of the County of Orange for all construction administration.
Bob Ledendecker
Director of Public Works/City Engineer
BL:jr