HomeMy WebLinkAboutRPT 3 C.T. WELL PROJ. 07-16-84 JULY 11., 1984 I rtl:er - C om
~TE':
FRO~:
$ USJ ECT:
WILLIAM HUSTON., CITY MANAGER
BOB LEDENDECKER., DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
COLUMBUS-TUSTIN WELL PROJECT STATUS REPORT
As requested by Councilman Edgar, the following is a continuing status report on
the subject project:
May 14, 1984 - Redevelopment Agency awarded contract for subject project
to low bidder, Stang Hydronics, Inc.
May 17., 1984 - Contracts mailed to Stang Hydronics in Rancho Cordova
for their execution.
June 12, 1984 - Stang Hydronics confirmed contracts in route to City by mail.
June 25, 1984 -
Contracts have not been received by the City - Contractor
assured Mr. Rowenhorst they were mailed June 22, 1984. Upon
receipt of the contracts, they will be disbursed to
appropriate parties for execution of contract. Start date is
dependent upon contract execution date.
July 10, 1984 - Pre-construction meeting held with Stang Hydronics.
July 12, 1984 - Expected start date for security fence installation.
July 16, 1984 - Expected start date for test hole.
Director of Public Works/City Engineer
BL:jr