HomeMy WebLinkAboutNB 2 WTR MAIN CONST. 05-21-84A · NEW BUSINESS
~' NO. 2
OATE: MAY 11, 1984
WILLIAM HUSTON, CITY MANAGER
FROM:
BOB LEDENDECKER, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
$ IJSJ ECT:
AWARD OF BID FOR WATER MAIN CONSTRUCTION -
LOCATION "A" - RED HILL AVE. FROM IRVINE BLVD. TO SKYLINE DR.
LOCATION "B" - LAGUNA RD. FROM RED HILL AVE. TO 200 FT. EASTERLY
RECOMMENDATION:
That the Tustin City Council, at their meeting of May 21, 1984, award the contract
for water main installation in Red Hill Ave. from Irvine Blvd. to Skyline Dr. and
Laguna Rd. from Red Hill Ave. to 200 ft. easterly to Macco Constructors., Inc. of
Paramount, California, the low bidder, in the amount of $166.,447.60 and authorize
a supplemental appropriation to the 1983-84 water budget in the amount of
$26,O00.00.
BACKGROUND:
On April 16, 1984~ the City Council authorized staff to advertise bids for water
main construction on Red Hill Ave. from Irvine Blvd. to Skyline Dr. and on Laguna
Rd. from Red Hill Ave. to 200 feet easterly. Thefe is presently $162.,500.00
budgeted in the 1983-84 budget for these projects.
DISCUSSION:
Bids for these projects were opened on May 11., 1984 at 10:00
received as follows:
Contractor
Business Location
Macco Constructors., Inc.
Schuler Engineering, Corp.
R & L Sewers., Inc.
John T. Mall oy
Thibodo Const. Co.., Inc.
Matt Ziach & Sons
Edmund J. Vadnais
Paramount, CA
Anaheim, CA
Paramount., CA
Los Angeles, CA
Vista., CA
Glendale, CA
Solana Beach~ CA
a.m. and were
Bid Amount
$166,447.60
$168,452.25
$179,311.50
$181,415.00
$185,881.00
$189,928.30
$213,512.75
The low bid is 9.1% under the Engineer's estimate of $183,204.00.
Attached, is a complete tabulation of all bids for the City Council's information.
In addition to the work to be performed under this contract, City personnelwill
be installing new domestic service laterals (34 total) and all connections located
at each of the intersecting streets along the length of the project. The
estimated material cost for this work performed by City forces is $22,000.00.
AWARD OF BID FOR WATER MAIN CONSTRUCTION
MAY 11., 1984
PAGE 2
This project will require a supplemental amount of $26,000.00 to be budgeted
within the current 1983-84 budget year.
Bob Led~ndecker
Director of Public Works/City Engineer
BL:jr