Loading...
HomeMy WebLinkAboutRDA STREET IMPROV'S 05-17-82AGEND DATE: MAY 12, 1982 REDEVELOPMENT AGENCY No. 6 5-17-82 Inter-Corn TO: FROM: S UBJ EI::T: WILLIAM HUSTON, EXECUTIVE DIRECTOR, TUSTIN ~TY REDEVELOPM~I~T AGENCY BOB LRDENDECKER, DIRECIOR OF PUBLIC WORKS/CITY ENGINEER EL CAMINO REAL/MAIN STREET IMPROVEMENTS Originally, this project was sdleduled for Council authorization to advertise for bids on May 17, 1982. As of this writing, the plan preparation has not ~cn totally completed by the consultant. It is anticipated that the consultant will be submitting the plans for review and checking to the City on May 28, 1982. It will take staff approximately 10 days to finalize the bid documents and complete the plan check review. Therefore, it is anticipated that the project will be on the agenda of June 7, 1982 for authorization to advertise for bids. DIRECTOR OF PUBLIC WORKS/ CITY ENGINEER db