EL CAMINO REAL/MAIN STREET IMPROVEMENTS
Due to extensive corrections to the plans and specifications for
the subject project, the staff report and resolution authorizing
the advertisement of bids will not be included in the Council
agenda packet. This item will be provided at the June 7, 1982
Redevelopment Agency meeting as a handout.
A representative of the consultant's firm will be available at
the meeting to answer any questions relating to the landscaping
and architectural amenities within the project.
BOB LEDE~DECKER
DIRECTOR OF PUBLIC WORKS/
CITY ENGINEER
db
DATE: JUNE 7, 1982
i~~~
Inter-Corn
TO: WILLIAM HUSTON, EXEC. DIRECTOR, TUSTIN COMMUNITY REDEVELOPMENT AGENCY
FROM: DALE WICK, ASSISTANT CITY ENGINEER
SUBJECT: AUTHORIZATION TO ADVERTISE FOR BIDS - EL CAMINO/MAIN STREET
IMPROVEMENTS
RECOMMENDATION:
It is recommended that the Tustin Community Redevelopment Agency, at their meeting
of June 7, 1982, pass and adopt the attached Resolution approving plans and
specifications for subject project and direct the secretary to advertise for bids.
I
BACKGROUND:
Subject project encompasses complete removal and reconstruction of curb and
gutter, sidewalk and street pavement on El-Camino Real between Newport and First
Street and on Main Street between Prospect and "C" Street. Said reconstruction
will encompass beautification items per previous approval of the Agency.
The Engineer's estimate for this work is $1,300,000.00. There is presently
$1,350,000.00 budgeted for this work and depending on bid results, it will
probably be necessary to budget an additional $90,000.00 in fiscal year 1982-83 to
cover Engineering and miscellaneous costs.
The tentative schedule for this project is as follows
AGENCY AUTHORIZATION TO ADVERTISE FOR BIDS.
FIRST LEGAL ADVERTISEMENT .
SECOND LEGAL ADVERTISEMENT.
OPEN BIDS .........
AGENCY AWARDS CONTRACT ....
BEGIN CONSTRUCTION .....
COMPLETE CONSTRUCTION . . .
JUNE 07, 1982
JUNE 24, 1982
JULY 01, 1982
· JULY 09, 1982
' JULY 19, 1982
AUGUST 02, 1982
.DECEMBER 15, 1982