HomeMy WebLinkAboutRPT 1 AHFP PROJ 1064 06-21-82AG-NDA : DATE: JUNE 3, 1982 later-eom TO: FROM: SUBJECT: WILLIAM HUSTON, CITY MNAGER DALE WICK, ASSISTANT CITY ENGINEER FINAL REPORT - RED HILL AVENUE AHFP PROJECT NO. 1064 COOPERATIVE AGREEMENT NO. D82-002 RECOMMENDATION: It is recommended that the City Council, at their meeting of June 21, 1982, receive and file subject final report. BACKGROUND: Subject project encompassed pavement rehabilitation and reconstruction on Red Hill Avenue between Lance Drive and Irvine Blvd. Total expenditures for the project including construction costs and engineering are as follows: COUNTY AHFP AND ROAD DEPARTMENT FUNDS ..... $100,364.19 CITY FUNDS .................. 81,062.88 TOTAL PROJECT COST . . . $181,427.07 Total City funds budgeted for this project was $107,800.00. Design and construction engineering for this project was done completely "in-house" and costs ran 6.3% or $10,830.96. Based on ASCE median compensation curves for this type of project, consulting engineering fees for this project would have been 8.3% or $14,150 for an estimated savings of $3,320.00. In addition, of the $10,830.96 expended for engineering, $5,991.61 will be reimbursed to the City from County funds. The AHFP procedural manual requires that the final report for AHFP projects be transmitted to the City Council for informational purposes. ASSISTANT CITY ENGINEER db cc: City Clerk Finance Di rector CITY OF TUSTIN FINAL REPORT AND FINAL ACCOUNTING AHFP PROJECT NO. 1064 COOPERATIVE PROJECT NO. D82-002 FOR PAVEMENT REHABILITATION AND PAVEMENT RECONSTRUCTION ON RED HILL AVENUE BETWEEN LANCE DRIVE AND IRVINE BOULEVARD TOTAL PROJECT COST $1 81, 427. 07 CITY OF TUSTIN AHFP PROJECT NO. 1064 COOPERATIVE PROJECT NO. D82-002 Final Report for the Improvement of Red Hill Avenue Between Lance Drive and 1trine Boulevard TYPE OF IMPROVEMENT: Pavement rehabilitation consisting of repair of deteriorated pavement areas, heater remix, and application of recycling agent to all remaining pavement areas and construction of a 0.15' thick asphalt concrete overlay overall. DESCRIPTION OF WORK PERFORMED: Remove deteriorated pavement and replace with 1.10' thick deep lift asphalt concrete, cold plane adjacent to all gutter edges, heater remix and apply recycling agent to all remaining pavement, construct 0.15' thick asphalt concrete overlay overall, adjust manholes and water valves to finished grade, and restore traffic striping. In addition, added to the project by contract change order was work consisting of recompacting of the existing Orange County Sanitation District No. 7 sanitary sewer trench between First Street and Irvine Blvd. LENGTH IN MILES: 0.59 ENGINEER IN CHARGE: Dale A. Wick DATE WORK BEGAN: March 25, 1982 DATE WORK COMPLETED: May 7, 1982 -1- CONTRACT COSTS ITEM NO. ITEM OF WORK QUANTITY 1. Sawcut 5,124 L.F. 2. Cold Plane 5,930 L.F. 3. Excavation 1,599 C.Y. 4. AC Base Course 2,522.27 Tons 5. Heater Remix 205,143 S.F. 6. Var. AC Overlay 120 Tons 7. 0.15' Thick AC Overlay 2,199.13 Tons 8. Adjust M.H. to Grade 13 Each 9. Adjust W.V. to Grade 23 Each 10. Traffic Striping 1 L.S. CCO #1 Sewer Trench Compaction 1 L.S. CCO #2 Aggregate Base 20.74 Tons CCO #2 Extra Work 1 L.S. WORK BY CITY FORCES AND OTHERS DESIGN ENGINEERING UNIT PRICE TOTAL AMOUNT $ 0.21 $ 1,076.04 0.525 3,113.25 5.95 9,514.05 22.03 55,565.61 0.11 22,565.73 24.35 2,922.00 24.35 53,548.82 150.00 1,950.00 110.00 2,530.00 2,291.00 2,291.00 7,500.00 7,500.00 5.95 123.40 7,896.21 7,896.21 TOTAL CONTRACT COST $170,596.11 LABOR Principal Engineer 35.5 Hrs. @ $16.38 . . $ 581.49 Principal Engineer 58.5 H'rs. @ 17.77 . . . 1,039.55 Engineering Aide 60 Hrs. @ 10.88 ...... 652.80 Overhead @ 18% ............... 409.29 EQUIPMENT 30 Miles @ 0.15 ............... MATERIALS & SUPPLIES Blueprinting ................ 4.50 71.42 . . $2,759.05 -2Z CONSTRUCTION ENGINEERING LABOR Principal Engineer 123 Hrs @ $17.77 . . . $2,185.71 Assistant Civil Engineer 14 Hrs. @ 13.89 .... 194.46 Public Works Inspector 112.5 Hrs. @ 12.13 . . 1,364.63 Engineering Aide 2 Hrs. @ 10.88 ......... 21.76 Engineering Aide 44.5 Hrs. @ 11.42 ....... 508.19 Overhead @ 18% ......... 759.86 +Consultant - Pave~e~t'RJclami~e'TJs~s .... 2,455.00 EQUIPMENT 200 Miles @ 0.15 ................ 30.00 MATERIALS & SUPPLIES Blueprinting .................. 42.82 Misc. Supplies ................. 15.00 . OTHER WORK BY CITY FORCES AND OTHERS *COUNTY EXPENSES Labor .................... $386.00 Equipment .................... 39.00 Overhead @ 18% ................. 69.48 . . TOTAL WORK BY CITY FORCES & OTHERS . . . $7,577.43 $494.48 $10,830.96 TOTAL COST OF PROJECT ...... $181,427.07 DIVISION OF COSTS COUNTY COOPERATIVE AH~DS CITY FUNDS PROJECT FUNDS CONTRACT COST ......... $66,523.53 WORK BY CITY FORCES & OTHERS . . 4,223.50 **TOTALS .... $70,747.03 $76,223.53 $27,849.05 4,839.35 1,768.11 $81,062.88 $29,617.16 TOTAL AMOUNT $170,596.11 10,830.96 $181,427.07 *See Page ¢ **See Exhibit 15, page 5 +See page 6 -3- ENgINEEEIN~ Matmrial Test Labor ~quipm~nt Overhead EXPENDITUI~S BY THE COUNTY OF ORANGE for the IMPROVSMENT OF R~D HILL AV~NLTE AHFP ~106& $ 326.00 39.00 125.00 $ 490.00 Soil ~est Labor $ 60. O0 Equir~ent -O- Overhead 22. O0 Less Overhead in excess of 18% Labor Total progress paTmen=s to City of Tustin TOTAL AMOUNT EXP~NDED BY COUNTY 82.00 S 572.00 77.52 494.48 61,600.00 $ 62,096.48 This is to certify' that no charges incurred prior to July i, 1979 are included in the above figures. tis Arnold, Chief lnancial Operations MC:gvAlO0(21) 5/21/82 -4- C$.JENT: City of Tustin Civic Center 300 Centennial Way Tustfn, CA 92680 Reclamite Study Red 'Hill Avenue AHFP No. 1064 RECEIVED APR g 9 5335 4/27/82 12788 UNITS Coring 4 hrs. $ Core Charge 39 in. Core Density & Thickness g Core Trimming 9 Extraction % Asphalt, Abson Recovery g Penetration on Original Asphalt 9 Penetration on Reclamite Treated Samples 14 Evaluation of Test Results & Report 2 hrs. UNIT COST TOTAl. c.q, il DI T BALANCE '1.50 58. 28.00 1.50 103.00 36,00 40.00 560.00 50.00 lO0.O0 $ 2,455.00 THANK YOU REMARKS There were no significant changes in estimated quantities, except as provided for by Contract Change Orders. The only significant deviation from approved plans consisted of heater remixing the travel lane adjacent to medians between Lance Drive and First Street and work as called for by Contract Change Orders. *There were two Contract Change Orders issued during the course of the work. These were necessary because of the fact that it was determined necessary to recompact the existing OSCD ~7 sewer trench prior to the heater remix and paving operation. This particular trench had been a continual problem for the City with frequent street failures occuring due to trench settlement. In 1972 and 1973, the City recompacted that portion of the trench between Lance Drive and First Street. The portion of the trench between First St. and Irvine Blvd. was not included in this project for recompaction because it was felt there had not been that much of a problem with it. However, just prior to the start of the work, a 115' long section of trench settled necessitating emergency street repairs. Subsequent investigation revealed that the entire trench between First St. and Irvine Blvd. had sub-standard compaction and for public safety reasons, it was decided to add this work to the project by Contract Change Order. These Change Orders are described as follows: CCO #1 - Provided for sawcutting and removing a 4.5' wide strip of pavement over the trench, removing the existing AB, jetting the trench, stomping the trench, and replacing the pavement with a 1.10' thick deep lift AC section. CCO #2 - Provided for compensating the Contractor for extra work involved during the trench recompaction work which was not anticipated. This work consisted in part of: (a) The existing AB was 2.0'± thick and had to be removed to permit penetration by the jet bar and more effective stomping. (b) During pavement removal, deep lift AC was encountered in several locations requiring special equipment to facilitate removal. (c) After jetting and stomping, the trench settled wider than the 4.5' width anticipated (in some locations up to 15' wide) requiring additional pavement removal and replacement. *See pages 9 & 10 -7- CONTRACTOR PERFORMANCE The Contractor's performance was excellent. The project was compacted one calendar day ahead of schedule. QUALITY OF WORK The City of Tustin is well satisfied with the quality of the work performed by the Contractor. QUA}:TITY SU~H~HY - THIS CCO ITEM' I~CREASP- NO. DESCRIPTION (DECREASE) AMOUNT E~T~ WO~ DESCriPTION . COST THIS CCO' TOTAL CHANGE PHEV. CCO'$ $ $ $ TOTAL TO DAT~ Percent Change CONTRACT CHANGE ORDER FOR APPROVAL TOTAL CHANGE COST SUMk~RY · THZS CCO PREV. CCO'S' Iacrease [decrease) of Contract Items TOTAL NON RON ~HFP AHF~ AHFP TOTAL TO DATE ~Og AHFP AHF? PHOTOGRAPHS BEFORE AFTER LOOKING NORTH FROM LANCE DRIVE LOOKING NORTH FROM 200' S. OF BRYAN AVE. PHOTOGRAPHS BEFORE AFTER LOOKING NORTH FROM STA. 13+50 LOOKING NORTH FROM FIRST ST. PHOTOGRAPIIS BEFOt~E AFTER LOOKING NORTH FROM STA. 20+00 LOOKING NORTH FROM STA. 24+00 PHOTOGRAPHS BEFORE AFTER LOOKING NORTH FROM STA. 29+00 LOOKING NORTH FROM STA. 32+00 CERTIFICATION We, the undersigned, Finance Director, City Engineer, and Project Engineer, certify that expenditures of $181,427.07 have been made in accordance with the provisions of our cooperative agreements for AHFP Project No. 1064 and D82-002. We have in our possession copies of invoices, auditors warrants, and other substantiating documents that such expenditures have been made. These documents are available for inspection upon request. We certify that this report is a true and correct statement of the work performed and costs incurred on the above project and that no charges incurred prior to July 1, 1979 are included in this report. DIRECTOR OF PUBLIC WORKS PROJECT ENGINEER CITY ENGINEER -15-