AWARD OF BID FOR EL CAMINO REAL/MAIN STREET IMPROVEMENTS
RECOMMENDATION:
That the Tustin Community Redevelopment Agency, at their meeting of July 19, 1982,
award the contract for subject project to R.J. Noble Co. Inc. of Orange, CA in the
amount of $1,201,141.50.
BACKGROUND:
Subject project encompasses complete reconstruction of pavement, curb & gutter,
sidewalk, and, in addition, includes landscaping, hardscapin9, and other
beautification items. The work will be accomplished on E1Camino Real from
Newport to First Street, E1 Camino Way from Santa Ana Freeway to E1 Camino Real,
and on Main Street from "C" Street to Prospect Avenue.
Sealed bids for this work were opened on July 9, 1982 at 10:00 AM and were
received as follows:
CONTRACTOR
R.J. Noble Co.
Griffith Co.
McGrew Const. Co. Inc.
Silveri & Ruiz Const. Co.
Sully-Miller Contracting Co.
T.J. Crosby Co. Inc.
BUSINESS LOCATION
Orange, CA
Santa Ana, CA
Anaheim, CA
Garden Grove, CA
Orange, CA
Santa Ana, CA
BID
$1,218,641.50
1,308,633.81
1,326,105.70
1,343,835.51
1,371,101.70
1,387,670.53
The low bid is 3.7% below the Engineer's estimate of $1,265,055.00. There is
presently $1,350,000.00 in RDA funds allocated for this work.
The actual recommended contract award amount is less than the low bid submitted
because the total low bid includes both Bid Items No. 82 and 83. Bid Item No. 82
is a bronze street clock with chimes. Bid Item No. 83 is an alternate cast iron
street clock without chimes, which was included in the event bids came in high and
it was found necessary to reduce costs. For low bid comparison purposes,
contractors were instructed to include both of these items in their total bid. In
light of the favorable bids received, staff is recommending the bronze street
clock with chimes. The recommended contract award amount reflects this
recommendation and the cost of the cast iron street clock without chimes has been
deleted from the contractor's low bid total.
AWARD OF BID FOR EL CAMINO REAL/MAIN STREET IMPROVEMENTS
JULY 13, 1982
PAGE TWO
Estimated total expenditures for this projet are as tabulated below:
Design Engineering .......
Construction ..........
Probable Contract Overruns . . .
Construction Engineering ....
Misc. Costs/Right of Way ....
TOTAL
$98,078.00
1,201,141.00
6O,000.00
62,000.00
7,000.00
$1,428,219.00
Attached for the Redevelopn~nt Agency's information is a tabulation of all bids
received.
DALE A. WICK
ASSISTANT CITY ENGINEER
db
Attachment
CC:
City Clerk
Finance Director
Street Maintenance Supt.