HomeMy WebLinkAboutRPT 4 WTR STUDIES 07-19-82AGENDA
DATE: JULY 9, 1982
REPORTS
NO. 4
7-19-82
Inter-Corn
TO:
S UBJ ECT:
WILLIAM HUSTON, CITY MANAGER
BOB LEDENDECKER, DIRECTOR OF PUBLIC WORKS/CITY EJtGINEER
WATER SERVICE STUDIES TIMETABLE
BACKGROUND:
The City has currently engaged a consultant, James M. Montgomery, Inc., to perform
a water system financial review and rate study of the Tustin Water Service and is
in the process of selecting a consultant firm to prepare the Water Service
Management Program and System Analysis. Per the City Council's request, a
timetable of events has been prepared for each study.
DISCUSSION:
Water Service Financial Review and Rate Study
Consultant: James M. Montgomery, Inc.
Required Time of Completion: 90 days
Consultant Commenced Work: 6/16/82
Consultant Completion Date: 9/14/82
Staff Review Completion Date 9/27/82
Presentation to City Council: 10/4/82
Water Service Management Program and System Analysis
Staff is still in the process of selecting a consultant for recommendation to the
City Council for this study from a final list of four consultants. As a result of
the consultant selection process not being completed as 6f this date, a firm
timetable for this study cannot be provided at this time. However, a quick review
of the proposals provides two possible timetables; the minimum and maximum times
required by the various consultants:
Staff Interview of Consultants: 7/19/82
Council Authorization to Award Contract:
Consultant Commences Work: 8/16/82
8/2/82
MINIMUM MAXIMUM
TIME TIME
Phase I Completion: 9/13/82
Phase II Completion: 1/3/83
BOB LEDENDECKER
DIRECTOR OF PUBLIC WORKS/
CITY ENGINEER
11/8/82
5/9/83
db