FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS -
FISCAL YEAR 1981-82 HANDICAPPED RAMP CONSTRUCTION PROGRAM
RECOMMENDATION:
It is recommended that the Tustin City Council, at their meeting of September 7,
1982, adopt the attached resolution accepting subject project and authorizing the
recordation of the Notice of Completion.
Assuming no claims or stop payment notices are filed within 30 days of the date of
recordation of the Notice of Completion, it is further recommended that the City
Council authorize payment of the final 10% retention amount ($861.40) at that
time. This amount together with previous payment of $7,752.60 represents 100% of
the final contract amount.
BACKGROUND:
Subject project encompassed construction of 23 wheelchair ramps at various
locations.
The work has been completed to the satisfaction of the Engineering Division and
there were no contract overruns or underruns on the project.
The final contract amount is $8,614.00. There is presently $8,813,00 in SB'821
Bicycle and Pedestrian funds budgeted for this project.
ASSISTANT CITY ENGINEER
db
Attachment
CC:
City Clerk
Finance Director
Street Maintenance Supt.
1 RESOLUTION NO. e2-74
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUSTIN ACCEPTING WORKS OF IMPROVEMENT AND
AUTHORIZING RECORDATION OF NOTICE OF
COMPLETION
6
WHEREAS, Nobest Incorporated, having a contract with the
7 City of Tustin to construct the hereinafter described public work
and improvement; and
8
WHEREAS, the City Engineer has duly certified to the
9 construction and completion of said public improvements
hereinafter mentioned in a manner satisfactory to the City
l0 Council of the City of Tustin; and
11 WHEREAS, the City Council finds that said.contractor has
completed said public improvement hereinafter more particularly
12 described in accordance with the provisions of the contract
documents and the notice of completion and acceptance of said
13 public work and improvement should be filed and payment of the
balance due said contract authorized in accordance with the
14 contract documents.
15 NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Tustin that said pubic work and improvement be, and the
16 same is hereby accepted. Said public work and improvement is
more particularly described as follows:
17
FISCAL YEAR 1981-82 HANDICAPPED RAMP CONSTRUCTION PROGRAM
18
AND BE IT FURTHER RESOLVED that the City Engineer of the
19 City of Tustin be, and is hereby authorized to execute and file a
notice of completion and acceptance of said public work and
20 improvement described herein as required by law.
21
22
PASSED AND ADOPTED at a regular meeting of the City Council
of the City of Tustin on 1982.
23
24
25
26
ATTEST:
MAYOR
27