HomeMy WebLinkAboutRDA ST IMPROVEMENTS 11-01-82TO:
FROM:
WILLIAM HUSTON, EXECUTIVE DIRECTOR
TUSTIN COMMUNITY REDEVELOPMENT AGENCY
BOB LEDENDECKER, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
DALE WICK, ASSISTANT CITY ENGINEER
SUBJECT:
EL CAMINO REAL/MAIN STREET IMPROVEMENTS
RE-CAP OF COST OVER-RUNS
Per the Agency's request, tabulated below are the various cost over-run items
known to date for subject project, with explanations of each item:
ITEM EXPLANATION TOTA ~OST
Extend 10" water main on
E1 Camino Real from 150' S.
of First Street to First St.
The 10" water main installed several
years ago on E1Camino Real was
stopped about 150 feet south of
First Street. It was felt that it
would be advisable to extend this
main northerly past the crosswalk to
prevent future dig-up of the inter-
locking pavers (or cobblestones as
some call them).
$6,109.80
e
Miscellaneous cost over-runs
in connection with water
main work.
This work consisted of water main
fittings, valves, and tapping
sleeves which were called for on the
plans, but not included as bid items
in the bid document.
6,493.50
3. Furnish and install "Tustin This item was requested and approved
Area Museum" sign. by the Redevelopment Agency. 3,653.00
0
Provide and place aggregate
base access ramps at drive-
ways and street inter-
sections.
This item was requested by the
Redevelopment Agency to provide
better access to businesses. The
total cost is based on estimated
tonnage. To date, approximately
$5,000.00 of the estimated cost of
$9,000.00 has been expended.
9,000.00
o
Construct new catch basin
at the northwest corner of
Main St. and Prospect Ave.
This catch basin was deleted from
the storm drain constructed last
year on Main Street between Prebble
and Prospect pending the downtown
redevelopment project. It was in-
advertently not included on the
plans for the E1Camino/Main Street
improvements.
5,083.25
RE-CAP OF COST OVER-RUN~
OCTOBER 25, 1982
PAGE TWO
ITEM
EXPLANATION
TOT~L COST
o
10.
Close-up skylights on north
side Main Street between
E1Camino Real and Prospect.
Replace existing steel
checker plate Edison vault
covers with decorative
covers,
Furnish, install and paint
wood sign posts for traffic
control and directional
signs.
Furnish and place aggregate
base for pavement subgrade.
Repair, replace, or lower
existing utility services.
This work was called for on the
plans, but not detailed or in-
cluded as a bid item in the bid
document.
The Engineer expended considerable
time working with the Edison Co. to
evolve a decorative cover which
Edison tentatively approved. After
bids were opened, Edison rejected
the cover called for on the plans.
A different type of cover had to be
specified with the resultant extra
cost.
It was the City's intent to replace
all steel channel sign posts with
wood posts stained to match the
decor of other hardscape items. The
plans and specs neglected to include
this item.
During the course of the work, a
shortage of dirt evolved due to the
fact that the existing pavement
being removed was much thicker than
anticipated. In addition, many
areas of unsuitable pumping or
boggy subgrade were uncovered. It
was determined to utilize aggregate
base to replace the dirt shortage
and dig out of the boggy areas and
replace with aggregate base. The
total cost is based on estimated
tonnage. To date, approximately
$11,000.00 of the estimated cost of
$15,000.00 has been expended.
It was discovered that many of the
water and gas services were laid
directly under the old sidewalk.
Some were broken during the side-
walk removal and many had to be
lowered to permit subgrade compac-
tion and installation of the new
sidewalk
$1,800.00
10,910.00
2,940.00
15,000.00
876.86
RE-CAP OF COST OVER-RUNS
OCTOBER 25, 1982
PAGE THREE
11.
12.
ITEM
Excavate roots and
deleterious material from
behind ficus trees and
replace with aggregate base.
Pump out abandoned gasoline
tanks and fill with cement
slurry.
13. Additional excavation.
14.
Additional decorative side-
walk pavers.
EXPLANATION
During the course of the sidewalk
work, it was found that the root
structure of the Ficus trees was so
extensive that the contractor was
unable to obtain proper compaction
for the sidewalk pavers. It was
determined that the roots should be
removed and replaced with aggregate
base to prevent future settlement
of the pavers.
During Phase III removals, two
abandoned underground gasoline tanks
were uncovered within the public
right-of-way at the Tustin Garage at
6th & E1Camino Real. Per Fire
Marshall requirements, it was
necessary to pump these tanks and
fil) with cement slurry. This work
necessitated hiring a special hauler
capable of hauling hazardous
material as well as obtaining a
State Hazardous Waste Permit.
Old State Highway plans indicated
that the existing concrete pavement
was 7" thick. Our records indicated
3" to 4" of asphalt concrete overlay
had been placed over this. The
contract excavation quantity was
based on a total of 11" thick pave-
ment removal. During the removals,
it was discovered that the pavement
in some areas was much thicker, up
to 18" total in some places. The
$20,000 over-run is an estimate for
the entire project since all re-
movals are not completed as of this
date.
To provide project uniformity, the
design architect determined that
additional sidewalk paver areas
should be added. During the rush
of meeting the plan submittal dead-
line, they had neglected to show on
the plans all of the decorative
sidewalk paver areas intended. An
additional 668 sq. ft. was added.
TOTAL COST
$4,966.56
845.04
20,000.00
2,571.80
RE-CAP OF COST OVER-RUNS
OCTOBER 25, 1982
PAGE FOUR
ITEM
EXPLANATION
TOTAL COST
15. Additional 6"x6" PCC header.
This is the concrete ribbon utilized
to retain the sidewalk pavers. The
quantity take-off utilized for the
bid document was in error by an
estimated 1,000 L.F.
$5,700.00
16.
Transfer excess dirt from
water main trench on Main
St. to low subgrade area
east side E1 Camino Real
between 1st & 3rd.
It was determined that contractor
should receive payment for this work
under provisions of State of Cali-
fornia specifications under which
this project is operating.
1,308.20
17. Miscellaneous
This item consists of miscellaneous
extra work ordered by the inspector
to expedite the project such as:
lowering existing traffic signal
conduits which were not originally
installed deep enough, misc. traffic
signal pull box modifications and
repairs, remove wet material to
expedite curb & gutter pour, crush
existing abandoned irrigation line
uncovered during removals and other
minor misc. work.
2,378.95
SUBTOTAL COST OVER-RUNS $99,636.96
The following items cannot be considered cost over-runs, but are project expenses
which:much be considered in the over-all cost of the project.
18.
ITEM
Blueprinting.
EXPLANATION TOTA~
Printing costs for this project are
very high due to the large number of
sheets involved (32) and the many
subcontractors who all must have
copies of plans. In addition,
during the bidding process, about 40
sets of plans & specs were taken out
by prospective bidders.
$1,536.40
RE-CAP OF COST OVER-RUNS
OCTOBER 25, 1982
PAGE FIVE
ITEM
EXPLJ~NATION
TOTAl. COST
19.
Soils and compaction test-
ing.
This is not normally a large item to
consider. In this case, due to the
urgency of completing the work, it
was necessary to ingage a private
laboratory for soils testing because
we could not get the required ser-
vice out of Orange County's lab.
By utilizing private industry, costs
have about doubled. The $8,000 cost
is an estimate of the amount to
complete the project. To date,
$5,401.85 has been expended.
$8,000.00
20. Film.
This is cost of film purchased to
keep a pictorial record of project
progress as requested by the Re-
development Agency. In addition,
the photos are utilized in the event
of any future litigation.
237.45
21. Barricades
This is cost of renting barricades
for the "Downtown Merchants are
Open for Business" signs as request-
ed by the Redevelopment Agency.
413.40
SUBTOTAL PROJECT EXPENSES $10,187.25
GRAND TOT~ COST OVER-RUNS & PROJECT EXPENSES $109,824.21
The Grand Total of $109,824.21 is still an estimated amount and it is conceivable
that this figure could increase or decrease depending on the results of the final
field measurements of all of the various contract items, which will be made when
the project is complete. Hopefully, the original contact quantities are accurate
enough so that there will be no significant increase from this estimated amount.
DALE A. WICK
ASSISTANT CITY ENGINEER
db