Loading...
HomeMy WebLinkAboutNB 1 PROJ M-M032(004) 12-19-83AGENDA OATE: DECEMBER 12, 1983 NEW BUSINESS NO. 1 12-19-83 Inter-Corn TO: WILLIAM HUSTON, CITY MANAGER FROM: DALE WICK, ASSISTANT CITY ENGINEER SUBJECT: MOULTON PARKWAY FAU PROJECT M-M032(004) APPROVAL OF MAJOR CONTRACT CHANGE ORDER RECOMMENDATION: It is recommended that the City Council by minute order approve the attached contract change order No. 10 for the Moulton Parkway FAU Project M-M032(O04). BACKGROUND: During the months of September, October and November of 1983 the contractor (SoCal Constructors) for subject project has been importing fill material for the Myford Road Bridge embankment. Toward the end of November we began to realize that it appeared there was going to be a substantial quantity overrun on embankment material since we were fast approaching the contract quantity and the roadway embankment was far from complete. Consequently, we.ordered a survey of material in place to determine material needed to complete the project. The results are that an-unanticipated $421,000.00 + will be required to complete this item of work, or an increase of 7.8% in th~ total contract amount. Contract change orders are normally approved by staff but because of the magnitude of this increase we felt that City Council approval should be obtained. Also, because the overrun on this item of work amounts to an 83% increase of this item, staff contacted the design consulting Engineer for an explanation for this increase. The Engineers response is attached. CalTraus has already approved this change order for 86.22% FAU participation and in addition, a portion of the embankment lies within the City of Irvine. The agency shares of the estimated $421,000.00 increase are as tabulated below: CalTrans FAU Share City of Tustin Share City of Irvine Share $362,960.00 39,200.00 18,840.00 TOTAL $421,000.00 The $421,000.00 figure is still an estimate, because contract specifications require that in the event of quantity overruns in excess of 25%, the contract unit price shall be adjusted. MOULTON PARKWAY FAU PROJECT M-M032(004) APPROVAL OF MAJOR CONTRACT CHANGE ORDER DECEMBER 12, 1983 PAGE 2 The contractor is presently looking for another source of material and the final increase will depend on what he has to pay for the material at the new source plus his trucking costs. The bottom line is that basically this change order corrects an error in quantity take-off. The overall cost increase to the project will be virtually nothing, since the work was there to do, but due to the take-off error our projected total project cost was too low. Dale A. Wick Assistant City Engineer and Resident Engineer for Moulton Parkway FAU Project Attachment VAN DELL and ASSOCIATES, INC. CIVIL ENGINEERS-SURVEYORS-LAND PLANNERS 17801 CARTWRIGHT ROAD, SUITE A IRVINE, CALIFORNIA 92714 AREA CODE 714 / 966-1100 December 6, 1983 Mr. Dale Wick City of Tustin 300 Centennial Way Tustin, CA 92680 Re: Moulton Parkway/Irvine Center Drive Dear Dale: In response to your November 17, 1983 letter the following comments concerning the import imbalance are offered. The basis for our estimate of import material was 105 lbs. per cubic foot. The contractor is using material having a unit weight of 130 lbs per cubic foot. The difference will result in a 24% increase in tonnage. The unit weight assumed for our estimate was discussed with our soils consultant during plan preparation. Our consultant indicated that the material may vary between 90 and 120 lbs per cubic foot and the mid-range, 105 lbs per cubic foot, was utilized for estimating purposes. The more dense material being used by the contractor will improve the R-value. Consideration may be given to reducing the structural section for the roadway since it was designed using an R-value of 10. A review of the backup calculations for the earthwork has been made. The fill requirements for the Myford Road embankment north of the railroad were omitted from the earthwork summary. There are approximately 38,000 cubic yards in this fill or 54,000 tons at 105 lbs per cubic foot. trust that this explanation will aid in resolving the issue. Sincerely, VAN DELL AND ASSOCIATES, INC. Johnnie Freeman, P.E. Project Engineer JLF: vb cc: Jim Castles, Pacific Soils CITY OF TUSTIN CONTRACT CHANGE ORDER NO. I0 CONTRACTOR ~ 0c::,4 (_ DESCRIPTION THIS CCO CHANGE IN CONTRACT ITEMS INCREASE (OECREASE) ITEM NO. DESCRIPTION UNIT PRICE QUANTITY AHOUNT 4 20, cy4 ,. ~' AOOITI'ONAL' WORK (NO ~ONTRACT ITEM) TOTAL $ AMOUNT DESCRIPTION TOTAL NET CHANGE SUH~ARY OF CONTRACT COST STATUS PRECEDING CCO CHANGES - INCREASE ~ DECREASE ~ - ................ ~--- THIS CCO CHANGE - INCREASE X OECREASE ACCEPTED~ SUBMITTED BY: '~4L~' APPROVED: City Eno n~ee~ NEW ESTIMATED CONTRACT COST APPROVAL RECOI~'I4ENOED: ~