HomeMy WebLinkAboutNB 3 STORM DR FACILTY 12-5-834GENDA
OATE:
NOVEMBER 30, 1983
NEW BUSINESS
NOo 3
12-5-83
Inter-Corn
TO:
FROM:
S UBJ ECT:
WILLIAM HUSTON, CITY MANAGER
JERRY OTTESON, ASSISTANT CIVIL ENGINEER
AWARD OF BID FOR MITCHELL AVE. STORM DRAIN FACILITY NO. S1P73 FROM
NEWPORT AVENUE TO "B" STREET
RECOMMENDATION:
It is recommended that the City Council, at their meeting of December 5, 1983,
award the contract for subject project to Bavin Construction Co. of La Habra Hts.,
CA. in the amount of $57,535.95, subject to final approval of the HCDA offices of
Orange County.
BACKGROUND:
The subject project is being funded by HCDA funds, of which the City has
$50,000.00 set aside for this first phase. It is anticipated that additional HCDA
funds will be allocated to make up the difference of $7,535.95. In the.event that
additional funds will not be allocated, the City will need to seek the additional
funds from other sources. ~
Bids for this project were opened on November 29, 1983 at 10:00 a.m. and were
received as follows:
Contractor Business Location Bid
Bavin Constr. Co.
J & B Contractors, Inc.
Dabco Construction
R & L Sewers
Forste$ Construction
Clarke Contracting, Inc.
Taylor-Sharer, Inc.
La Eabra Hts., CA
Crestline, CA
Huntington Beach, CA
Paramount, CA
Fullerton, CA
Compton, CA
Long Beach, CA
$57,535.95
57,868.46
65,981.62
68,858.74
71,143.75
80,624.30
85,793.00
The low bid is 15% over the Engineer's estimate of $49,034.54.
Attached, for the City Council's information, is a tabulation of all bids
received.
Jerry Otteson
Assistant-Civil Engineer
jr