DATE AUGUST 26, 1983 l~te~-Com
FI~OM:
$ UBJ ECT:
WILLIAM HUSTON, CITY MANAGER
DALE WICK, ASSISTANT CITY ENGINEER
AWARD OF BID FOR F.Y. '82-'83 HANDICAPPED RAMP CONSTRUCTION PROGRAM
RECOMMENDATION:
It is recommended that the City Council, at their meeting of September 6, 1983,
award.the contract for subject project to Arm & Hamn~r Concrete Removal of Tustin,
CA in the amount of $20,386.93 and authorize staff to add approximately 20
additional ramp locations to the project in order to utilize all of the available
funds for this work.
BACKGROUND:
This project encompasses construction of 66 wheelchair ramps at various locations
throughout the City, the majority of the locations being on Bryan Avenue between
Newport and Red Hill and on Walnut Avenue easterly of Red Hill..
Bids for this project were opened on August 26, 1983 and were received as follows:
CONTRACTOR BUSINESS LOCATION BID
Arm & Hammer Concrete Removal
Gabi Const. Co. Inc.
J.T. Garza Const. Inc.
Gutierrez Const. Co.
Changing Times Enterprises Inc.
Steve Pandza Constructors
Tustin
La Habra, CA
Paramount, CA
Fountain Valley, CA
Buena Park, CA
Norco, CA
$20,386.93
20,952.00
21,797.73
23,621.83
23,949.50
24,375.00
The low bid is 20% below the Engineer's estimate of $25,631.50. There is
presently $26,951.00 in SB 821 Bicycle and Pedestrian funds available for this
work.
Attached for the City Council's information is a tabulation of all bids received.