HomeMy WebLinkAboutNB 1 STORM DRN IMPROV 06-20-83DATE: JUNE 10, 1983
TO:
FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
DALE WICK, ASSISTANT CITY ENGINEER
AWARD OF BID FOR F.Y. '82-'83 STORM DRAIN IMPROVEMENTS
· LOCATIONS A,B, & C
RECOMMENDATION:
It is recomn~nded that the Ci'ty Council, at their meeting of June 20, 1983, award
the contract for subject project to Desatoff Construction Co. of Hacienda Heights,
CA in the amount of $262,832.00 and authorize staff to add $9,000.00 in additional
work to the project to construct a new catch basin at the N.E. corner of Newport
Avenue and Nisson Road.
BACKGROUND:
Subject project encompasses construction of storm drain improvements as follows:
LOCATION A - On Red Hill Avenue from Walnut to Mitchell and on Mitchell
Avenue westerly to connect to an existing dry Etorm drain that was
constructed in conjunction with Frontier Park.
LOCATION B - On the northerly side of Main Street between Pasadena and the
Costa Mesa Freeway. This drain will eliminate the existing drainage ditch at
this location which presently drains the Pasadena cul-de-sac.
LOCATION C - Project consists of*construction of catch basins on Red Hill
Avenue at Industrial Drive and Santa Fe Drive. When the storm drain in Red
Hill Avenue was originally constructed, it was constructed as a dry drain and
provisions were made for these catch basins, but they were not installed; the
intent being to install the basins when the downstream outlet for the Red
Hill Storm Drain was completed. This outlet was completed several years ago.
Bids for this project were opened on June 10, 1983 at 10:00 AM and were received
as follows:
CONTRACTOR BUSINESS LOCATION BID
Desatoff Construction Co.
Forster Construction
Kershaw Construction Co.
Valverde Construction Inc.
Schuler Engineering Corp.
Vicco Construction Inc.
G.R. Frost Inc.
Savala Construction Co.
Hacienda Heights, CA
Garden Grove, CA
Montclair, CA
Santa Fe Springs, CA
Anaheim, CA
La Verde, CA
Wilmington, CA
Costa Mesa, CA
$262,832.00
270,184.53
283,018.90
295,067,46
299,217.75
300,180.90
300,758.00
369,062.03
A~ARD OF BID FOR F.Y. '82-'83 STORM DRAIN IMPROVEMENTS
LOCATIONS A,B, & C
JUNE 10, 1983
The low bid is 6.5%' below the Engineer's estimate of $280,362.60. There is
presently $277,000.00 allocated in the F.Y. "82-'83 budget for these three
locations.
The authorization requested to add additional work to the contract will solve a
drainage/maintenance problem which exists at the N.E. corner of the intersection
of Newport Avenue and Nisson Rd. The estimated cost to construct a catch basin,
storm drain lateral and appurtenant work to solve this problem is $9,000.00. This
additional amount would put the total contract amount at $271,832.00, which would
still allow for $5,168.00 in budgeted funds to cover any additional expenses which
may be encountered during the course of the work.
Attached for the City Council's information is a tabulation of all bids received.
DALE A. WICK
ASSISTANT CITY ENGINEER
db
.Attachment
cc: City Clerk Finance Director
Street Maintenance Superintendent